| |
Peak-Load Reduction Program
Program Opportunity Notice (PON)
835
$10.5 million available for summer peak demand reduction measures
|
Applications accepted on a first-come,
first-served basis through
November 1, 2004, 3:00 PM EST.*
|

Entire document in 755kb .pdf
The Peak-Load Reduction Program is one of the programs offered under
the umbrella of the New York Energy $martSM Program.
The New York State Energy Research and Development Authority (NYSERDA),
as administrator of the New York Energy $martSM
Program, requests applications from Eligible Contractors (as defined
herein) to identify and implement one or more Project(s) (as defined
herein) which will result in reduced peak electric demand in New York
State, particularly New York City, for the summer of 2004 through
four distinct program components: Permanent Demand Reduction Efforts
(PDRE), Load Curtailment/Shifting (LC/S), Dispatchable Emergency Generator
Initiatives (DEGI), and Interval Meters (IM).
Eligible Contractors are facility owner/operators or service providers
capable of both developing electric demand-reduction Projects and
implementing all necessary measures. Facilities eligible for PDRE,
LC/S, and IM are limited to electric distribution customers of New
York State's investor-owned utilities that pay into the System Benefits
Charge (SBC). Facilities eligible for DEGI are limited to electric
distribution customers only within the Con Edison service territory
which pay into the System Benefits Charge (SBC).
APPLICATION SUBMISSION: Applications must be clearly labeled
and mailed to:
Ann Travison PON 835
New York State Energy Research and Development Authority
17 Columbia Circle
Albany, New York 12203-6399
All program questions should be directed to Christopher
Smith (866-NYSERDA, ext. 3360, cjs@nyserda.org)
or Peter Savio (866-NYSERDA, ext. 3334, or pps@nyserda.org).
Contractual questions should be directed to Mary Sauvie (866-NYSERDA,
ext. 3229, or mks@nyserda.org).
For questions regarding the New York Independent System Operator's
(NYISO's) Demand Response Programs, contact Aaron Briedenbaugh at
NYISO (518) 356-6023, or go to www.nyiso.com.
________________
* Faxed or e-mailed applications will not be accepted. Applications
will not be accepted at any NYSERDA location other than the address
specified above. Applications will be processed on a first-come, first-served
basis through November 1, 2004, 3 PM Eastern Time or until funds are
fully committed, whichever comes first.
Table of Contents
I. INTRODUCTION
A. OBJECTIVE
B. AVAILABLE FUNDS
C. INCENTIVES
D. LIMITATIONS
E. APPLICATION PROCESS
F. DEFINITIONS
II. PROGRAM REQUIREMENTS - REIMBURSEMENT INCENTIVES
A. PERMANENT DEMAND REDUCTION EFFORTS (PDRE)
1. Eligibility
2. Minimum Project Size
3. Incentives
B. LOAD CURTAILMENT/SHIFTING (LC/S)
1. Eligibility
2. Minimum Project Size
3. Incentives
C. DISPATCHABLE EMERGENCY GENERATOR INITIATIVES (DEGI)
1. Eligibility
2. Minimum Project Size
3. Incentives
4. Required Mitigation Measures
D. INTERVAL METERS (IM)
1. Eligibility
2. Minimum Project Size
3. Incentives
III. PROJECT IMPLEMENTATION PROCESS
A. PDRE, LC/S, AND DEGI PROJECTS
B. INTERVAL METER PROJECTS
IV. METERING REQUIREMENTS
V. REPORTING REQUIREMENTS
A. INTERMEDIATE REPORTS
B. FINAL REPORTS
VI. PROGRAM EVALUATION
VII. NON-COMPLIANCE
VIII. DISCLAIMER
IX. APPLICATION REQUIREMENTS
X. GENERAL CONDITIONS
APPENDICES
APPENDIX A - APPLICANT CHECKLIST
APPENDIX B - FACILITY DATA SHEETS
B1 Permanent Demand Reduction Efforts
B2 Load Curtailment/Shifting
B3 Dispatchable Emergency Generator Initiatives
B4 Interval Meters
APPENDIX C - SAMPLE PURCHASE ORDERS
EXHIBIT A PROGRAM COMPONENT DETAILS
EXHIBIT B STANDARD TERMS AND CONDITIONS
EXHIBIT C PROMPT PAYMENT POLICY STATEMENT
APPENDIX D - TECHNICAL ASSESSMENT OUTLINES
APPENDIX E - CONTRACTOR CHECKLIST
APPENDIX F - INVOICE COVER SHEET
APPENDIX G - REPORTING REQUIREMENTS
I. INTRODUCTION
A. OBJECTIVE
The objective of PON 835 is to improve electric system reliability
and system load factor, as well as reduce electric costs by providing
incentives that result in system coincident electric summer peak demand
reduction in New York State, particularly in New York City. Incentives
are offered to Contractors to develop and implement peak load reduction
Project(s) that meet this objective. Measures installed under PON
835 must perform as an integrated function without compromising applicable
building code requirements or occupant health, comfort, or safety.
All measures must exceed efficiency requirements contained in applicable
codes or regulations. The customer baseline load profile and strategy
for accomplishing peak load reductions must be clearly delineated
in the Technical Assessment (see Appendix D).
The integrated program consists of four components: (See Section
II, Program Requirements - Reimbursement Incentives for a complete
description of eligibility requirements and program administration).
Permanent Demand Reduction Efforts (PDRE) result in reduced
peak demand during the Summer Peak Demand Reduction Period, through
the installation of equipment that provides long-term (expected to
be in place and operational for at least five years), overall system
coincident peak demand reduction. Capital improvements requiring design
and installation periods of greater than 8 months are encouraged to
investigate the Commercial/Industrial Performance Program (CIPP),
and/or other NYSERDA funded programs.
Load Curtailment/Shifting (LC/S) results in reduced peak demand
either in response to an electric capacity shortfall, or defined price
signal. Each participating Facility must register in a New York Independent
System Operator (NYISO) Demand Response Program (DRP), an Acceptable
Load Serving Entity (LSE) Load Management Program, or a Time of Use
(TOU) or Real Time Pricing (RTP) Program for at least one entire Summer
Peak Demand Reduction Period.
Dispatchable Emergency Generator Initiatives (DEGI) result
in reduced peak demand at times of capacity shortfall, by enabling
owners of existing emergency/backup generators in the Con Edison service
territory to offload all, or a percentage of their electric capacity
requirements to their own generators, in response to a communication
from the New York Independent System Operator's Demand Response Program
(EDRP or ICAP/SCR), or a Transmission Owner Load Management Program
for at least one entire Summer Peak Demand Reduction Period.
Interval Meters (IM) result in reduced peak demand through
the purchase and installation of Interval Meters and communications
to enable participation in load reduction programs such as the NYISO's
Demand Response programs, and/or an Acceptable LSE Load Management
Program, including a TOU or RTP program for at least one entire Summer
Peak Demand Reduction Period.
Eligible Contractors are encouraged to investigate other New York
Energy $mart programs, including the Commercial/Industrial Performance
Program, the New Construction Program, Smart Equipment Choices, Technical
Assistance, Distributed Generation/Combined Heat & Power (DG/CHP)
Program, and the Loan Fund Program. These programs offer incentives
for the purchase and installation of energy efficient equipment. See
NYSERDA's website (www.nyserda.org) for more information on each of
these programs.
B. AVAILABLE FUNDS
NYSERDA has up to $10.5 million available for incentives to Contractors
under this solicitation. The program terms offered through this PON
are effective as of November 1, 2003. Section I (C)(4). addresses
program incentive caps by Contractor, Facility and Project.
Applications will be processed on a first-come, first-served basis
until all funds are committed, or through November 1, 2004, whichever
is earlier. Contractors awarded an incentive will be issued one or
more Purchase Orders from NYSERDA.
C. INCENTIVES
Three types of incentives are available: a reimbursement incentive,
an aggregation incentive, and a controllable appliance aggregation
incentive pilot.
1. Program Incentive Caps
(a.) Unless otherwise approved by NYSERDA, the total incentive per
Contractor under this Program will not exceed 20% of the total funding
for this solicitation (initial Contractor cap - $2.1 million), excluding
the Aggregation Incentive and the Controllable Appliance Aggregation
Incentive Pilot.
(b.) The total incentive per Facility for measures under this Program
will not exceed 7% of the total funding for this solicitation (initial
Facility cap - $735,000).
(c.) Contractor and/or Facility caps may be adjusted based on program
activity and funding resources.
(d.) The total incentive for the DEGI component of the Program will
not exceed 30% of the total funding of this solicitation (initial
DEGI cap - $3.15 million).
2. Reimbursement Incentives
TABLE 1 - Reimbursement Incentive Caps 1,
3
|
PDRE
|
LC/S
|
DEGI
|
IM
|
|
Con
Edison
Service
Territory
|
Non-
Con
Edison
Service
Territory
|
Con
Edison
Service
Territory
|
Non-
Con
Edison
Service
Territory
|
Con
Edison
Service
Territory only
|
Statewide
PSC Approved
|
Statewide
NYISO
Compliant
|
|
$475/kW
|
$225/kW
|
$175/kW
|
$45/kW
|
$125/kW
|
$2,500
per meter 2
|
$1,200
per meter 2
|
1 NOTE: Contractors will be reimbursed the lesser of 70% of the Eligible
Project Costs or the incentive caps set forth in Table 1. The Facility
owner/operator must contribute no less than 30% of Eligible Project
Costs.
2 NOTE: New York State Public Service Commission Approved Interval
Meters will be reimbursed the lesser of 70% of Eligible Project Costs
or $2,500/meter, NYISO Compliant Interval Meters will be reimbursed
the lesser of 70% of Eligible Project Costs or $1,200/meter. Field
Verification is required for certain Interval Meter only Projects.
3 An Aggregation Incentive and Controllable Appliance Aggregation
Incentive Pilot are also available. (See Section (C), (3) and (4)
for details.)
Eligible Facilities must contribute to the SBC at the time of application
and continue to pay it throughout the program. In the event the customer
pays the SBC on less than 50 percent of the total annual electric
consumption (kWh) at the Facility, the incentive will be prorated
accordingly.
The Contractor will be reimbursed the lesser of 70% of the Eligible
Project Costs or the incentive caps set forth in Table 1. The Facility
owner/operator must contribute no less than 30% of Eligible Project
Costs and take ownership of all measures funded under PON 835. NYSERDA
reserves the right to require documentation from the Contractor to
demonstrate the Facility owner/operator's minimum payment requirement.
NYSERDA reserves the right to require canceled checks to verify that
Eligible Project Costs have been incurred.
The final reimbursement incentive payment will be determined, per
PON 835 and the Purchase Order (PO), including Exhibit A, based on
an approved Technical Assessment (developed by the Contractor) and
Field Verification of equipment installed and operational, as outlined
in the Technical Assessment, and appropriate Facility specific invoices.
These incentives may be modified if the approved Technical Assessment
and/or approved Field Verification identify changes to the estimated
kW demand reduction. Ineligible Project costs include, but are not
limited to, Facility labor, or ongoing expenses such as subscription
fees, software licensing fees, service/maintenance fees, communications
or internet fees, etc.
No more than 30% of the Eligible Project Costs shall be for project
development. Project development includes administrative costs, overhead,
engineering, marketing, development of the Technical Assessment, travel
expenses, profit, or other expenses approved by NYSERDA. No less than
70% of the Eligible Project Costs shall be for project implementation.
Project implementation includes only direct expenses for the purchase
and installation (labor and material costs) of equipment at the Facility,
such as on-site operation and maintenance improvements, energy management
system upgrades, advanced metering, Direct Load Control (DLC) technologies,
disposal fees, or other expenses approved by NYSERDA. Eligible Project
Costs must be specifically itemized for each Facility, including materials
and equipment expenses, staff names and titles identified, billable
hourly rates, tasks performed, and hours applied to specific tasks.
Invoice items must be specifically identified as project development
expenses or project implementation expenses. All invoices must include
a signed invoice cover sheet, included in Appendix F. Invoice requirements
apply to all invoices submitted, including Contractor invoices and
subcontractor invoices. NYSERDA will inform all Facilities of incentives
provided to their Contractor.
3. Aggregation Incentive
Contractors who aggregate at least 8 MW of new, Field Verified ICAP/SCR
demand reduction in the Con Edison service territory under PON 835
are eligible for a $100,000 aggregation incentive. Upon receipt of
applications from a single Contractor equaling or exceeding 8 MW of
ICAP/SCR demand reduction, NYSERDA will issue a purchase order to
the Contractor for $100,000. Aggregation incentives will be paid in
two installments: 40% after Field Verification, and 60% when the Contractor
verifies, by way of final report(s) to NYSERDA, that no less than
80% of demand reductions have been achieved as confirmed by the final
report(s) (see Appendix G) accepted by NYSERDA. Final reports to NYSERDA
must use the same demand reduction calculation methodology as required
by NYISO ICAP/SCR, and must be Facility-specific. Technical Assessments,
Field Verifications, and final reports must confirm that a single
Contractor has completed Projects resulting in greater than 8 MW of
demand reduction. Demand reductions resulting solely from the installation
of Interval Meters are not eligible to receive the aggregation incentive.
Facility-specific NYISO test data will be deemed sufficient in the
event that ICAP/SCR resources are not called upon during the Summer
Peak Demand Reduction Period.
The PON 835 Aggregation Incentive is to support the development
and implementation of demand response projects that deliver NEW ICAP/SCR
demand response resources. The Aggregation Incentive is limited to
technology and infrastructure improvement-based demand response Projects
- not behavior-based demand response Projects. Eligible Project Costs
must be at least $500,000, and enable 8 MW of demand reduction to
receive the Aggregation Incentive. The Aggregation Incentive is limited
to one award per NYSERDA Contractor.
The Aggregation Incentive is to deliver new demand response resources
at a diversity of Facilities, through a diversity of Contractors and
Responsible Interface Parties (RIP), to foster a vibrant and competitive
demand response market. To this end, NYSERDA will closely monitor
the distribution of Aggregation Incentive awards, and the Facilities,
Contractors and CSPs involved. Should NYSERDA see a concentration,
rather than a diversity, the Aggregation Incentive may be adjusted
accordingly.
4. Controllable Appliance Aggregation Incentive Pilot
This incentive is for the replacement of existing equipment with the
following new appliances, which have integrated DLC devices and are
installed in the Con Edison service territory:
Room Air Conditioners/Thru-the-Wall Air Conditioners
Packaged Terminal Air Conditioners
Packaged Terminal Heat Pumps
Hard-wired Lighting Fixtures
Electric Domestic Water Heaters
These appliances must have integrated DLC capability, must participate
in the PDRE and LC/S components of this solicitation, and must be
installed at Facility(ies). Existing appliances must be removed and
de-manufactured or scrapped in an environmentally sound manner, and
the Contractor must provide proof that this requirement has been met.
The DLC device must be installed inside the appliance, integrated
in the operation of the appliance, in such a way that the appliance
becomes inoperable if the DLC device is tampered with or removed.
The DLC integrated appliance must deliver both efficiency improvements
over the equipment being replaced and demand response capability.
The demand reduction must be provided through an Acceptable LSE Load
Management Program to provide demand reduction during the Summer Peak
Demand Reduction Period.
The Controllable Appliance Aggregation Incentive Pilot will reimburse
the lesser of 70% of the costs of the appliance or $1,000/kW reduction.
The demand reduction must include both permanent demand reduction
and curtailable load. The Controllable Appliance Aggregation Incentive
Pilot is limited to one award per NYSERDA Contractor. This incentive
is not available for DLC integrated appliances currently available
in the marketplace.
The total funding available under the Controllable Appliance Aggregation
Incentive is $500,000 and will be awarded on a first-come first-serve
basis for NYSERDA approved Projects. NYSERDA may adjust this project
incentive cap and/or funding cap based on program activity. Up to
$250,000 per Project is available under the Controllable Appliance
Aggregation Incentive. The Appliance Aggregation Incentive is payable
upon Field Verification that the units have been installed in accordance
with the criteria herein. Contractors may proceed with the manufacture
and installation of the appliances after submission of an application
for incentives and before approval by NYSERDA, but do so at their
own risk.
Direct Load Control must be used to dispatch the DLC integrated
appliance product. The minimum installation of the integrated DLC
appliances is 200 units and must enable a minimum of 200 kW of load
reduction, which must include PDRE and LC/S.
The application must include a detailed description of the appliance
to be installed, including the following:
1. The specific make and model appliance to be installed and controlled.
The appliance efficiency must be greater than the appliance being
replaced and must exceed all applicable State and Federal energy efficiency
standards.
2. The Direct Load Control technology (proprietary, open protocol,
etc.), the communication protocol (radio frequency, cellular, carrier
signal, internet, intranet, etc.), the Eligible Contractor or entity
responsible and their methodology to monitor and dispatch load control,
control methodology (part load, duty cycling, load anticipation logic,
modulating, temperature reset, etc.), and Facility and Contractor
override details.
3. A detailed description of the development and manufacture of the
appliance, in particular to address specifics regarding design, setup
and testing needs of DLC integration. This must include detail as
to the manufacturing design, setup and testing requirements and costs.
4. The intended Project site(s) of the appliances. List Facility(ies)
where appliances are to be installed, number of appliances to be installed,
and base case and proposed DLC enabled operating schedule of the appliances
during the Summer Peak Demand Reduction Period.
5. Identify the Demand Response program(s) in which the Facility(ies)
will register. Describe the dispatch criteria under which the demand
response resources will be implemented. If demand response resources
are to be economically dispatched, identify price signals, intended
dispatch hours, etc.
6. The business plan and market potential for broad based application
of the integrated DLC technology in this appliance across New York
State.
D. LIMITATIONS
Eligible Project Costs must be incurred between November 1, 2003 and
March 31, 2005. Measures for which expenses have been incurred prior
to November 1, 2003 are ineligible for incentives. Incentives are
limited to equipment and services procured under contracts signed
after November 1, 2003. All Purchase Orders expire on April 29, 2005,
unless the Contractor provides acceptable written justification by
January 31, 2005, for the delay in completing the Project. NYSERDA
will not make payment on an expired Purchase Order. Incentives awarded
under PON 835 cannot pay for measures funded under other NYSERDA programs
including previous releases of the Peak Load Reduction Program. Single
family residences are ineligible, except for select aggregated Facilities.
The Contractor is responsible for obtaining all required local, state,
and federal permits, and is responsible for complying with all applicable
building, health, environmental, and safety codes.
E. APPLICATION PROCESS
The application process begins when the Applicant submits a completed
application to NYSERDA (see Appendix A for the Contractor and Appendix
B1-B4 for the Facility), on behalf of one or more Facilities. All
applications must be submitted by an Eligible Contractor. For aggregated
Projects, only one Appendix A per submitted aggregation is required,
although one or more Appendix B must be completed for each Facility.
Appendix B must describe each Project for a particular Facility and
indicate an estimated summer peak kW demand reduction for each Facility.
The Applicant Checklist is located in Appendix A, Facility Data Sheets
are located in Appendices B1-B4, sample Purchase Orders are located
in Appendix C, a Technical Assessment outline is attached as Appendix
D, a Contractor Checklist is located in Appendix E, an Invoice Cover
Sheet is located in Appendix F and the Final Report format is located
in Appendix G.
F. DEFINITIONS
Acceptable LSE Load Management Program - Load management programs,
such as TOU or RTP, or NYISO's DRPs, intended to motivate electric
consumers to reduce on-peak electric demands. Programs must be offered
by Load Serving Entities or Transmission Owners, and must be acceptable
to NYSERDA and/or the Public Service Commission.
Applicant - Any entity submitting an application under this solicitation
Project for a SBC-eligible Facility.
B20 - a blended Biodiesel mixture consisting of 20% (by volume)
Biodiesel and 80% (by volume) petro-diesel fuel.
Biodiesel - A fuel consisting of long-chain fatty acid alkyl esters
made from renewable vegetable oils, recycled cooking greases, or animal
fats that meets ASTM standard D6751with properties similar to #2 petroleum
diesel fuel.
Contractor - Any Applicant awarded a Purchase Order under this solicitation.
Curtailment Service Provider (CSP) - A load reduction aggregator,
energy service company (ESCO), or electric utility authorized, but
not required, to provide load reductions under the New York Independent
System Operator's Emergency Demand Response Program (NYISO's EDRP),
or its Day Ahead Demand Response Program (DADRP).
Direct Load Control (DLC) - A load reduction strategy that can interrupt
consumer load or modify settings or schedules of equipment at the
time of a NYISO or LSE peak demand period, or in conjunction with
Time of Use or Real Time Pricing programs. Equipment must be controlled
for an aggregated set of Facilities, by way of remote, centrally dispatched
communication/control. Notwithstanding any other provisions of this
solicitation, DLC Projects are eligible for all building types.
Diversity - A ratio of the equipment's average demand over the Summer
Peak Demand Reduction Period to the maximum connected demand of that
equipment.
Eligible Contractor - An Eligible Contractor must be capable of,
or must retain services capable of, developing a summer peak demand
reduction Project, and implementing all necessary measures. Eligible
Contractors include individual building owners or operators, lease
holders, energy services companies, Load Serving Entities, transmission
and/or distribution utilities, Demand Response Providers, equipment
installers, engineering firms, and energy management firms. See Section
VII. NON-COMPLIANCE for additional eligibility requirements.
Eligible Project Costs - Costs incurred between November 1, 2003
and March 31, 2005, associated with the development and implementation
of the measures necessary to achieve the Project's objectives, in
accordance with the Purchase Order, Exhibits A and B, and as outlined
in this Program Opportunity Notice. Ineligible Project costs include
Facility labor, ongoing expenses such as subscription fees, software
licensing fees, service/maintenance fees, communications/internet
fees, etc.
Facility - The location where the Project is proposed and implemented.
To be eligible for this program, a Facility must pay into the System
Benefits Charge at the time of application and continue to pay it
throughout the Program.
Field Verification - The final site visit, performed by NYSERDA,
or its Consultant, to verify that the measures identified in the Technical
Assessment have been installed, are operational, and are capable of
delivering the kW reduction as documented in the Technical Assessment.
Interval Meters - The Interval Meters component provides two distinct
functions: meters that capture time sensitive energy use information;
and communication systems that store and communicate energy use information.
PSC Approved Interval Meters - Interval Meter approved by the
New York State Public Service Commission, and installed by a Meter
Service Provider, in a configuration compliant with the New York
State Public Service Commission to be used for billing purposes.
Interval Meters installed under this component must be capable of;
1) supporting Time of Use and Real Time Pricing rate plans and 2)
providing read-only access, by direct ethernet connection, of revenue
grade data to the Facility or a designated agent of the Facility.
NYISO Compliant Interval Meters - Interval Meter that is compliant
with the NYISO regulations as they pertain to NYISO's DRP. NYISO
Compliant Interval Meters can be less accurate and are not revenue
grade.
Load Serving Entity (LSE) - Any entity authorized or required by
law, regulatory authorization or requirement, agreement, or contractual
obligation to supply energy, capacity and/or ancillary services to
retail end users located within the New York Control Area (NYCA),
including NYISO direct customers. For purposes of this PON, eligible
LSE's must demonstrate the presence of a New York State office.
Meter Service Provider - Entities approved by the New York State
Public Service Commission to install meters to be used for billing
purposes in New York State.
NYISO - New York Independent System Operator.
NYISO's EDRP - New York Independent System Operator's Emergency Demand
Response Program.1
NYISO's ICAP/SCR - New York Independent System Operator's Installed
Capacity/Special Case Resources Program.1
NYISO's DRP - New York Independent System Operator's Demand Response
Programs, including the Day Ahead Demand Response Program (DADRP),
Emergency Demand Response Program (EDRP), Installed Capacity Program
(ICAP), Special Case Resources (SCR), Unforced Capacity Program (UCAP),
and virtual bidding.
NYSERDA Consultant - An engineering consultant under contract to
NYSERDA to provide technical support and field verification services
for this program.
Project - The implementation of demand reduction and load management
measure(s) at a Facility by an Eligible Contractor.
Qualifying Direct Load Control Projects - An aggregated set of 25
or more buildings, resulting in at least 1,000 kW of controllable
load. All aggregated buildings must be controlled by a CSP or RIP,
as authorized by the NYISO.
Qualifying Generators - All customer owned/operated generators,
model year 1995 or newer; or all model year 1994 and older generators
that demonstrate either by generator specific manufacturer's data
or through emissions testing, that NOx emissions do not exceed 35
pounds per megawatt-hour (lb/MWh). Emissions testing methods for test
and tune purposes should be conducted consistent with industry established
protocols (such as the American Society for Testing and Materials
[ASTM] D6522-00) and applicable DEC regulations.
Real Time Pricing (RTP) - A market-based electric rate alternative
that informs consumers of dynamic pricing, typically reflecting periods
of electric capacity scarcity resulting in increased prices and periods
of surplus with reduced prices.
Responsible Interface Party (RIP) - An aggregator, authorized by the
NYISO, to administer demand response resources under the Installed
Capacity Special Case Resource Program.
Summer Peak Demand Reduction Period - May 1 to October 31, during
the hours of 11:00 A.M. to 7:00 P.M. This period may be adjusted on
a case-by-case basis to reflect certain night peaking load pockets.
Technical Assessment (TA) - A site specific, engineering or feasibility
study describing peak load Permanent Demand Reduction Efforts, Load
Curtailment/Shifting, and/or Dispatchable Emergency Generator Initiatives,
the methodology for determining kW demand reduction and kWh savings,
a summary of pre- and post- installation coincident kW demand and
kWh use, and measure costs (see Appendix D).
Time of Use Pricing (TOU) - An electric rate alternative that offers
pre-determined, time-sensitive rates for defined periods that reflect
the costs of providing energy and capacity to a customer.
Transmission Owner - The public utility or authority (or its designated
agent) that owns facilities used for the transmission of energy in
interstate commerce and provides transmission service under a New
York PSC approved tariff.
Ultra Low-Sulfur Fuel - Distillate fuel oil having a sulfur content
less than or equal to 30 parts per million by weight.
II. PROGRAM REQUIREMENTS - REIMBURSEMENT INCENTIVES
A. PERMANENT DEMAND REDUCTION EFFORTS (PDRE)
1. Eligibility
- Measures implemented under this component are to be installed
and operational at the Facility for at least five years.
- Measures must be operational and reduce demand at a Facility during
the entire Summer Peak Demand Reduction Period, consistent with
the measures' normal operating schedules.
- Measures must be activated in an automatic mode as an integrated
function of the operation of the building systems or equipment.
- Lighting measures must be hard-wired installations. Screw-in lamps
and/or screw-in ballasts, power quality and power factor improvements,
and lighting power reducers are ineligible for funding under this
component of the program.
- Heat island mitigation strategies that are building integrated,
such as window film or reflective roof coatings, are eligible measures.
- Fuel cells, wind turbines, Photovoltaic (PV), or other renewable
energy resources are eligible for funding under this component of
the program.
- Demand reductions resulting from the installation of the following
fossil-fuel fired generators are ineligible for funding under this
component of this solicitation: microturbines, internal combustion
engine-driven electric generation, and combined heat and power equipment.
- PDRE measures resulting in increased Facility emissions will be
considered on a case by case basis.
2. Minimum Project Size
The minimum Project size is 20 kW. Contractors are encouraged to aggregate
Projects to meet the minimum project size.
3. Incentives
- Eligible Project Costs include engineering services, procurement
and installation of capital equipment, or other NYSERDA approved
expenses incurred to permanently reduce summer peak demand.
- Diversity factors must be applied to all demand reduction measures.
Demand reductions that do not occur consistently between the hours
of 11:00 A.M. and 7:00 P.M. will be prorated accordingly.
- Capital equipment includes equipment improvements that result
in reduced electric demand, such as heating, ventilation and air-conditioning
(HVAC) equipment, lighting equipment, motors, PV, and select motor
drives.
For Projects in the Con Edison Service Territory:
The lesser of 70% of Eligible Project Costs or $475/kW of summer
peak demand reduction for measures installed, operational, and
Field Verified on or before March 31, 2005.
For Projects Outside the Con Edison Service Territory:
The lesser of 70% of Eligible Project Costs or $225/kW of summer
peak demand reduction for measures installed, operational, and
Field Verified on or before March 31, 2005.
B. LOAD CURTAILMENT/SHIFTING (LC/S)
1. Eligibility
- Contractors must show registration or proof of each Facility's
participation for no less than one entire Summer Peak Demand Reduction
Period in a NYISO DRP, an Acceptable LSE Load Management Program,
or a TOU or RTP program, and that each Facility is willing and technically
capable of receiving, and responding to a communication, or price
signal.
- Each LC/S Project, must have the willingness and technical capability
to curtail electric load at least 12 times, for a duration of not
less than four hours per curtailment, for a total of no less than
48 hours over the Summer Peak Demand Reduction Period.
- Facilities participating only in TOU or RTP programs must control
load in an automatic fashion to be eligible for funding under Load
Curtailment/Shifting.
- Non-aggregated residential customers are ineligible to receive
funding under Load Curtailment/Shifting.
- The Project must include installed measures that enable curtailing
or shifting electric use during the entire Summer Peak Demand Reduction
Period.
- Demand reductions resulting from the installation of new generation
or co-generation equipment are ineligible.
2. Minimum Project Size
For non-DLC Projects, the minimum proposed demand reduction Project
shall be at least 100 kW. Contractors are encouraged to aggregate
Projects to meet the minimum project size.
3. Incentives
Incentives will be paid to the Contractor upon receipt of all required
deliverables and reports, regardless of whether or not there is a
communication from NYISO or LSE during the Summer Peak Demand Reduction
Period.
- Eligible Project Costs include engineering services, procurement
and installation of capital equipment, metering equipment, and development
of a curtailment plan. Capital equipment includes equipment that
reduces electric demand, such as controls and improvements to heating,
ventilation and air-conditioning (HVAC) equipment, lighting, process
loads, motors, and motor drives. Training of Facility staff, and
other related expenses to develop and implement projects will be
considered on a case-by-case basis.
- The expenses for closing of a Facility, loss of revenue due to
the closing of a Facility as a Load Curtailment/Shifting measure,
or additional staff costs due to shifting operations to off-peak
hours are ineligible for an incentive.
- The NYSERDA funded kW demand reduction shall not exceed that which
is registered with the NYISO or an Acceptable LSE Load Management
Program.
- Qualifying Direct Load Control Projects are eligible for up to
100% of project cost.
- Contractors receiving the Controllable Appliance Aggregation Incentive
are ineligible for 100% DLC reimbursement.
For Projects in the Con Edison Service Territory:
The lesser of 70% of Eligible Project Costs or $175/kW of summer load
curtailment for measures installed, operational, and Field Verified
on or before March 31, 2005.
Qualifying Direct Load Control Projects, are eligible for the lesser
of 100% of Eligible Project Costs or $175/kW of summer load curtailment
for measures installed, operational, and Field Verified on or before
March 31, 2005.
For Projects Outside the Con Edison Service Territory:
The lesser of 70% of Eligible Project Costs or $45/kW of summer load
curtailment for measures installed, operational, and Field Verified
on or before March 31, 2005.
Qualifying Direct Load Control Projects, are eligible for the lesser
of 100% of Eligible Project Costs or $45/kW of summer load curtailment
for measures installed, operational, and Field Verified on or before
March 31, 2005.
C. DISPATCHABLE EMERGENCY GENERATOR INITIATIVES (DEGI)
1. Eligibility
- Qualifying Generators (see definition) within the Con Edison service
territory are eligible for incentives under the DEGI component.
- NYSERDA will fund switchgear, emissions reduction technology,
environmental permitting, and other acceptable ancillary equipment
associated with new generators, provided the generators meet the
following criteria. New units must document manufacturer specific
equipment NOx emission rates not-to-exceed 18 lbs/MWh. New units
must document manufacturer specific equipment PM10 emissions rates
not-to-exceed 0.70 lbs/MWh.
- Where newly installed units are replacements, existing units must
be removed and de-manufactured or scrapped, and the Contractor must
provide proof that this requirement has been met.
- Generator specific manufacturer's data is considered adequate
documentation for the Contractor to demonstrate that the equipment
meets the not-to-exceed NOx requirement. Eligible Contractors may
modify or tune emergency generators in order to meet emission requirements
of a Qualifying Generator.
- Contractors must show registration or proof of each Facility's
participation, for no less than one entire Summer Peak Demand Reduction
Period, in the NYISO's EDRP, ICAP/SCR, or a Transmission Owner Load
Management Program.
- Facilities must have the willingness and technical capability
to operate during the entire Summer Peak Demand Reduction Period,
but need only operate when it receives a communication from the
NYISO or a Transmission Owner. Each NYSERDA approved DEGI Project
must have the capability to operate at least 12 times, for a duration
of not less than four hours, for a total of no less than 48 hours,
and no more than 200 hours, over the Summer Peak Demand Reduction
Period.
- The project must be comprised of installed measures that enable
emergency generators to be operated solely in response to a communication
from NYISO's EDRP or ICAP/SCR, or a Transmission Owner Load Management
Program.
- Contractors and Facilities should be aware that DEC is currently
in the process of revising regulations applicable to distributed
generation resources. Generators that meet the requirements of this
solicitation are not assured that such units will meet future regulatory
requirements.
- Contractors must self certify that all Facilities with generators
have applied for or received all required State and local permits
or registrations necessary to operate the generators in a demand
response program.
2. Minimum Project Size
The minimum Project size is 100 kW.
3. Incentives
Incentives will be paid to the Contractor upon receipt of all
required deliverables and reports, regardless of whether or not there
is a communication from NYISO's EDRP or ICAP/SCR, or a Transmission
Owner Load Management Program during the Summer Peak Demand Reduction
Period.
- Eligible Project Costs include engineering services, procurement
and installation of metering equipment, testing and tuning of emergency
generators, improvements to reduce environmental impacts, incremental
cost of Ultra Low-Sulfur Fuel or Biodiesel (a blend no less than
B20), rewiring circuits, installation of transfer switchgear, environmental
permitting, selective use of catalytic reduction technologies, stack
modifications, operational improvements, implementation of natural
gas dual-fuel options, and eligible replacement units. Other related
costs will be considered on a case-by-case basis.
- NYSERDA will calculate the incentive based on the actual load
connected to the generator (as TA approved and field verified).
This demand reduction shall not exceed that which is registered
with the NYISO's EDRP or ICAP/SCR, or a Transmission Owner Load
Management Program.
For Projects in the Con Edison Service Territory ONLY:
The lesser of 70% of Eligible Project Costs or $125/kW of dispatchable
emergency generation for Qualifying Generators installed, operational,
and Field Verified on or before March 31, 2005.
4. Required Mitigation Measures
To further mitigate environmental impacts of this program, NYSERDA
will purchase and retire NOx allowances equal to twice the total calculated
NOx emissions generated from this component. NOx emissions will be
based on the actual hours of operation of the emergency generators
and an average NOx emission rate of 35 lb/MWh for all participants
of this component. The allowances will be purchased in one block at
the end of the Summer Peak Demand Reduction Period.
D. INTERVAL METERS (IM)
1. Eligibility
- Contractors must show registration or proof of each Facility's
participation for no less than one entire Summer Peak Demand Reduction
Period, in a NYISO DRP, an Acceptable LSE Load Management Program,
or a TOU or RTP program, and that each Facility is capable of receiving,
and responding to a communication, or price signal.
- Interval Meters are to be operational at the Facility(ies) for
at least two years.
- Interval Meters are to be used to enable and verify kW demand
reductions for NYISO DRP, an Acceptable LSE Load Management Program,
or TOU or RTP program for non-residential customers.
- Interval Meters installed at points other than the main electrical
feed(s), generators, or installations of three or more meters at
a single Facility must provide a Technical Assessment and must receive
prior approval from NYSERDA.
- NYSERDA must be provided read-only access to data, for a minimum
period of two years, to all Interval Meters funded by PON 835.
2. Minimum Project Size
The minimum Project size is 40 kW, but any Interval Meter enabling
less than a 40 kW demand reduction will be considered on a case-by-case
exception basis.
3. Incentives
Eligible Project Costs are limited to the purchase and installation
of individual metering systems that are connected to the following:
1) main electrical feeds (i.e. utility service entrance or master
meter point), 2) equipment that can reasonably be curtailed, or 3)
emergency/backup generator equipment.
For Interval Meters Installed Statewide:
PSC Approved Interval Meters are eligible for the lesser of 70% of
Eligible Project Costs or $2,500/meter. Such Interval Meters must
be approved by the New York State Public Service Commission, and installed
by a Meter Service Provider, in a configuration compliant with the
New York State Public Service Commission to be used for billing purposes.
Interval Meters installed under this component must be capable of;
1) supporting Time of Use and Real Time Pricing rate plans and 2)
providing read-only access, by direct ethernet connection, of revenue
grade data to the Facility or a designated agent of the Facility.
NYISO Compliant Interval Meters are eligible for the lesser of 70%
of Eligible Project Costs or $1,200/meter. Such Interval Meters must
be compliant with the NYISO regulations, as they pertain to NYISO's
DRP.
III. PROJECT IMPLEMENTATION PROCESS
A. PDRE, LC/S, AND DEGI PROJECTS
Unless noted otherwise, each of the following steps must be completed
to receive payment. A checklist is provided in Appendix E.
1. Eligible Contractor submits application to NYSERDA on or before
November 1, 2004. If the completed application meets all program criteria,
NYSERDA will encumber funds for that Project, and issue a Purchase
Order.
2. Once a Purchase Order is issued, a NYSERDA Consultant will be
assigned to the Contractor's Project at no cost to the Contractor.
The Consultant is assigned to the Project to review demand reduction
measures identified and recommended in the Technical Assessment and
to complete a Field Verification. The NYSERDA Consultant will contact
the Contractor.
3. The Contractor must submit a completed Technical Assessment to
their assigned NYSERDA Consultant for a review of technical accuracy
within 70 days of receipt of the Purchase Order, otherwise, the Purchase
Order may be voided. See Appendix D for Technical Assessment Outlines.
4. The NYSERDA Consultant reviews the Technical Assessment for technical
accuracy and provides recommendations to the Contractor concerning
the proposed kW savings within ten (10) business days of receipt of
the Technical Assessment. It is the Contractor's responsibility to
address and resolve all issues raised by the NYSERDA Consultant regarding
the technical accuracy and feasability of the Technical Assessment.
5. The NYSERDA Consultant provides its recommendations to NYSERDA,
who will notify the Contractor whether or not the Technical Assessment
is approved. If approved, NYSERDA will issue a notice-to-proceed,
stating the Technical Assessment-approved kW demand reduction. Any
Contractor proceeding with implementation of the Project before receiving
a notice-to-proceed from NYSERDA does so at its own risk.
6. Upon receipt of the notice-to-proceed, the Contractor shall proceed
to implement measures as specified in the approved Technical Assessment.
7. Upon Project completion, the Contractor must contact their assigned
NYSERDA Consultant to schedule the post-installation Field Verification.
Once the Contractor notifies the NYSERDA Consultant of Project completion,
the NYSERDA Consultant must conduct a post-installation Field Verification
visit.
8. Upon completion of the Field Verification, the NYSERDA Consultant
will provide written documentation to NYSERDA summarizing its technical
review of the Project installation and providing a recommended final
kW of summer peak demand reduction. If approved by NYSERDA, a notice-to-invoice
will be sent to the Contractor, verifying that completed measures
have been approved and stating the final adjusted kW demand reduction
based on the Field Verification and actual operation of the equipment.
If the kW summer peak demand reduction from the Field Verification
is greater than the amount shown on the Purchase Order, the Purchase
Order will be amended to reflect the increased incentive, provided
sufficient funds still exist in the program.
9. Upon receipt of complete deliverables, the Contractor receives
the incentive. Deliverables required in order to receive the incentive
are: 1) Appendix F accompanied by copies of Facility specific vendor
invoices and documentation to verify project development and project
implementation, 2) the notice-to-proceed from NYSERDA verifying approval
of the Technical Assessment, 3) documentation from the Contractor
demonstrating that the Facility owner/operator has contributed the
required minimum payment of no less than 30% of Eligible Project Costs,
and 4) for Load Curtailment/Shifting, Dispatchable Emergency Generation
Initiative, and Interval Meter Projects, proof of registration in
one or more of the acceptable demand reduction programs. NYSERDA reserves
the right to require additional deliverable documentation as necessary.
10. Contractor provides NYSERDA all required reports and meter data
access.
B. IM PROJECTS
Each of the following steps must be completed to receive payment.
A checklist is provided in Appendix E. If three or more Interval Meters
are being installed at a single Facility, follow the steps outlined
above in Section III (A).
1. Eligible Contractor submits application to NYSERDA.
2. Once a Purchase Order is issued, the Contractor shall proceed
to have the Interval Meters installed and made operational.
3. The Contractor may submit an invoice only after all meters within
a Purchase Order are installed and made operational.
4. Interval Meters installed at points other than the main electrical
feed(s) or generators, or a Facility installing three or more meters,
must provide a Technical Assessment and must receive prior approval
from NYSERDA.
5. Upon receipt of complete deliverables, the Contractor receives
the incentive. Deliverables required in order to receive the incentive
are: 1) A description of the specific metering improvements and their
locations and installation points, 2) Appendix F accompanied by copies
of Facility specific vendor invoices, 3) access to metered data, and
4) proof of program participation in a NYISO DRP, an Acceptable LSE
Load Management Program, or other load reduction programs offered
by LSEs, including Real Time or Time of Use pricing.
6. Contractor provides all required reports and meter data access
to NYSERDA.
IV. METERING REQUIREMENTS
All projects with 100kW or more of summer peak demand reductions
are required to permanently install and make Interval Meters operational.
Metering equipment meeting the definition of Interval Meters in this
PON will be deemed adequate. Hourly metered data must be archived
for two years, and be made available to NYSERDA upon request, in appropriate
electronic format. If this metered data is provided via website, the
data must be made available to NYSERDA in read-only format. Metered
data must be made available to NYSERDA for a two-year period. Contractors
shall obtain written consent from their clients to permit NYSERDA
access to this data. This data will be used only for internal analysis,
future program development purposes, and verification of demand reductions.
All data shall be protected to the fullest extent possible under the
New York State Freedom of Information Law.
V. REPORTING REQUIREMENTS
A. INTERMEDIATE REPORTS
For the LC/S, DEGI, and IM components, each time a Contractor or Facility
is required to submit a report to the NYISO or an Acceptable LSE Load
Management Program for incentive payments as part of a load management
program, a copy of that report shall be sent to the Peak-Load Reduction
Program at NYSERDA within five (5) business days of the submission
of the report to the NYISO or an Acceptable LSE Load Management Program.
B. FINAL REPORTS
By April 29, 2005, each Contractor participating in this Program shall
submit a final report to NYSERDA. See Appendix G for final report
format. Failure to provide all required reports will render the Contractor
ineligible for NYSERDA's Peak-Load Reduction Program in the current
year (2004) as well as for the anticipated 2005 program.
VI. PROGRAM EVALUATION
NYSERDA requires Contractors who participate in PON 835 to respond
to surveys and to provide feedback through program evaluations to
assess program effectiveness. Failure to cooperate with evaluations
may result in ineligibility for NYSERDA programs.
VII. NON-COMPLIANCE
Contractors may be deemed to be in non-compliance with this program
for any of the following: 1) Contractors fail to meet at least 80%
of demand reductions or dispatched emergency generation, as contracted
by the final NYSERDA incentive, 2) Contractors fail to submit the
final report as required in Section V. REPORTING REQUIREMENTS of this
solicitation, 3) Contractors fail to submit copies of NYISO DRP or
an Acceptable LSE Load Management Program reports to NYSERDA as required
in Section V. REPORTING REQUIREMENTS of this solicitation, or 4) Contractors
that have not complied with program requirements in a timely manner.
Contractors deemed to be in non-compliance shall have their PO cancelled
and shall become ineligible for any or all future Peak-Load Reduction
Programs.
VIII. DISCLAIMER
NYSERDA's receipt and acceptance of the Technical Assessment shall
not constitute any representation by NYSERDA as to the economic or
technical feasibility, operational capability, or reliability of the
information contained in the Technical Assessment. NYSERDA's payment
of the incentive to the Contractor shall in no way represent an endorsement
by NYSERDA of any findings or recommendations contained in such TA.
IX. APPLICATION REQUIREMENTS
Applicants must fill out the Applicant Checklist (Appendix A) and
the appropriate Facility Data Sheet(s) (Appendix B(s)), completely,
leaving no blank information. This information will be used to determine
the incentive award. For ease of use, the application package is also
available on NYSERDA's website. Paper copies of application forms
and the application checklist must contain an original signature.
Applications aggregating two or more Facilities must list each Facility
on separate application forms (B1, B2, B3, etc.), identifying the
estimated summer peak demand reduction expected at each Facility.
A Facility with multiple buildings may be aggregated into one Facility
Data Sheet.
X. GENERAL CONDITIONS
Proprietary Information - Careful consideration should be
given before confidential information is submitted to NYSERDA as part
of your proposal. Review should include whether it is critical for
evaluating a proposal, and whether general, non-confidential information,
may be adequate for review purposes.
The NYS Freedom of Information Law, Public Officers law, Article
6, provides for public access to information NYSERDA possesses. Public
Officers Law, Section 87(2)(d) provides for exceptions to disclosure
for records or portions thereof that "are trade secrets or are
submitted to an agency by a commercial enterprise or derived from
information obtained from a commercial enterprise and which if disclosed
would cause substantial injury to the competitive position
of the subject enterprise." Information submitted to NYSERDA
that the proposer wishes to have treated as proprietary, and confidential
trade secret information, should be identified and labeled "Confidential"
or "Proprietary" on each page at the time of disclosure.
This information should include a written request to except it from
disclosure, including a written statement of the reasons why the information
should be excepted. See Public Officers Law, Section 89(5) and the
procedures set forth in 21 NYCRR Part 501.
Omnibus Procurement Act of 1992 - It is the policy of New
York State to maximize opportunities for the participation of New
York State business enterprises, including minority- and women-owned
business enterprises, as bidders, subcontractors, and suppliers on
its procurement Agreements.
Information on the availability of New York subcontractors and suppliers
is available from:
Empire State Development
Division For Small Business
30 South Pearl Street
Albany, NY 12245
A directory of certified minority- and women-owned business enterprises
is available from:
Empire State Development
Minority and Women's Business Development Division
30 South Pearl Street
Albany, NY 12245
Contract Award - NYSERDA anticipates making multiple awards
under this solicitation. It may award a contract based on initial
applications without discussion, or following limited discussion or
negotiations. NYSERDA may request additional data or material to support
applications. NYSERDA expects to notify applicants in approximately
four weeks from the receipt of application whether your application
has been selected to receive an award.
Limitation - This solicitation does not commit NYSERDA to
award a contract, pay any costs incurred in preparing a proposal,
or to procure or contract for services or supplies. NYSERDA reserves
the right to accept or reject any or all proposals received, to negotiate
with all qualified sources, or to cancel in part or in its entirety
the solicitation when it is in NYSERDA's best interest.
Disclosure Requirement - The proposer shall disclose any indictment
for any alleged felony, or any conviction for a felony within the
past five years, under the laws of the United States or any state
or territory of the United States, and shall describe circumstances
for each. When a proposer is an association, partnership, corporation,
or other organization, this disclosure requirement includes the organization
and its officers, partners, and directors or members of any similarly
governing body. If an indictment or conviction should come to the
attention of NYSERDA after the award of a contract, NYSERDA may exercise
its stop-work right pending further investigation, or terminate the
agreement; the contractor may be subject to penalties for violation
of any law which may apply in the particular circumstances. Proposers
must also disclose if they have ever been debarred or suspended by
any agency of the U.S. Government or the New York State Department
of Labor.

Entire document in 755kb .pdf
|
|