| |
 |
Peak Load Reduction Program
Program Opportunity Notice
(PON) No. 733-02
Revision
June 9, 2003
|
$11 million available for summer peak demand reduction measures
|
Applications accepted on a first-come,
first-served basis through October 31, 2003, 3:00 PM EST*
|
Significant Changes effective 6/9/03
Major changes include, but are not limited to:
Adding incentive for interval meters not covered by the New
York State Public Service Commission regulations and clarification
of the aggregation incentive.
40 kW reduction (lower reductions per meter
will still be considered on a case-by-case basis); and requiring
the facility owner/operators to contribute no less than 30%
of eligible project costs for certain measures.
In addition, "Table 1 - Project Incentive
Caps" was revised to specifically include incentives
for interval meters not covered by the New York State Public
Service Commission regulations (see table below).
Revised TABLE 1 - Project Incentive Caps1,
2
| PDRE |
LC/S |
DEGI |
IM |
|
Con Edison
Service Territory
|
Non-
Con Edison
Service Territory
|
Con Edison
Service
Territory
|
Non-
Con Edison
Service Territory
|
Con Edison
Service Territory only
|
Statewide
PSC Approved
|
Statewide
NYISO Compliant
|
|
$475/kW
|
$175/kW
|
$175/kW
|
$55/kW
|
$125/kW
|
$2,500 per meter3
|
$1,200 per meter3
|
1 NOTE: Contractors will be reimbursed the lesser of
70% of the Eligible Project Costs or the incentive caps set
forth in Table 1. The Facility owner/operator must contribute
no less than 30% of Eligible Project Costs.
2 NYSERDA reserves the right to increase program
incentives within the Con Edison service territory.
3 NOTE: New York State Public Service Commission
Approved Interval Meters will be reimbursed the lesser of
70% of Eligible Project Costs or $2,500/meter, NYISO Compliant
Interval Meters will be reimbursed the lesser of 70% of Eligible
Project Costs or $1,200/meter. Field Verification may not
be required for Interval Meter only Projects.
|
The Peak-load Reduction Program is one of the programs offered under
the umbrella of the New York Energy $martSM program.
The New York State Energy Research and Development Authority (NYSERDA),
as administrator of the New York Energy $martSM
Program, requests applications from Eligible Contractors (as defined
herein) to identify and implement one or more Project(s), as defined
herein, which will result in reduced peak electric demand in New York
State, particularly New York City, for the summer of 2003 through
four distinct program components: Permanent Demand Reduction Efforts
(PDRE), Load Curtailment/Shifting (LC/S), Dispatchable Emergency Generator
Initiatives (DEGI), and/or Interval Meters (IM).
Eligible Contractors are facility owner/operators or service providers
capable of both developing electric demand-reduction Projects and
implementing all necessary measures. Facilities eligible for PDRE,
LC/S, and IM are limited to electric distribution customers of New
York State's investor-owned utilities that pay into the System Benefits
Charge (SBC). Facilities eligible for DEGI are limited to electric
distribution customers only within the Con Edison service territory
which pay into the System Benefits Charge (SBC).
APPLICATION SUBMISSION: Applications must be clearly labeled
and mailed to:
Lee L. Smith, PON No. 733-02
New York State Energy Research and Development Authority
17 Columbia Circle
Albany, New York 12203-6399
Technical questions should be directed to Christopher Smith
(866-NYSERDA, ext. 3360, cjs@nyserda.org)
or Peter Savio (866-NYSERDA, ext. 3334, or pps@nyserda.org).
Contractual questions should be directed to Mary Sauvie (866-NYSERDA,
ext. 3229, or mks@nyserda.org).
For questions regarding the New York Independent System Operator's
(NYISO's) Demand Response Programs, contact Dave Lawrence at NYISO
(518) 356-6084, or dlawrence@nyiso.com, or go to www.nyiso.com.
________________
* Faxed or e-mailed applications will not be accepted. Applications
will not be accepted at any other NYSERDA location other than the
address specified above. Applications will be processed on a first-come,
first-served basis through October 31, 2003, 3 PM Eastern Standards
Time or until funds are fully committed, whichever comes first. Table
of Contents
I. INTRODUCTION
A. OBJECTIVE
B. AVAILABLE FUNDS
C. INCENTIVES
D. LIMITATIONS
E. APPLICATION PROCES
F. DEFINITIONS
II. PROGRAM REQUIREMENTS
A. PERMANENT DEMAND REDUCTION EFFORTS (PDRE)
1. Eligibility
2. Minimum Project Size
3. Incentives
B. LOAD CURTAILMENT/SHIFTING (LC/S)
1. Eligibility
2. Minimum Project Size
3. Incentives
C. DISPATCHABLE EMERGENCY GENERATOR INITIATIVES (DEGI)
1. Eligibility
2. Minimum Project Size
3. Incentives
4. Required Mitigation Measures
D. INTERVAL METERS (IM)
1. Eligibility
2. Minimum Project Size
3. Incentives
III. PROJECT IMPLEMENTATION PROCESS
A. PDRE, LC/S, AND DEGI PROJECTS
B. INTERVAL METER PROJECTS
IV. METERING REQUIREMENTS
V. REPORTING REQUIREMENTS
A. INTERMEDIATE REPORTS
B. FINAL REPORTS
VI. PROGRAM EVALUATION
VII. NON-COMPLIANCE
VIII. DISCLAIMER
IX. APPLICATION REQUIREMENTS
X. GENERAL CONDITIONS
APPENDICES
APPENDIX A - APPLICANT CHECKLIST
APPENDIX B - FACILITY DATA SHEETS
B1 Permanent Demand Reduction Efforts
B2 Load Curtailment/Shifting
B3 Dispatchable Emergency Generator Initiatives
B4 Interval Meters
APPENDIX C - SAMPLE PURCHASE ORDERS
EXHIBIT A PROGRAM COMPONENT DETAILS
EXHIBIT B STANDARD TERMS AND CONDITIONS
EXHIBIT C PROMPT PAYMENT POLICY STATEMENT
APPENDIX D - TECHNICAL ASSESSMENT OUTLINES
APPENDIX E - CONTRACTOR CHECKLIST
APPENDIX F - INVOICE COVER SHEET
I. INTRODUCTION
A. OBJECTIVE
The objective of PON 733-02 is to offer an integrated program to improve
electric system reliability and system load factor, as well as to
reduce electric costs by providing incentives that result in system
coincident electric summer peak demand reduction in New York State,
particularly in New York City. Incentives are offered to Contractors
to develop and implement peak load reduction project(s) that meet
this objective. Measures installed under PON 733-02 must perform as
an integrated function without compromising applicable building codes
or occupant health, comfort, or safety. All measures must exceed efficiency
requirements contained in applicable codes or regulations. For the
purposes of the application, the baseline for estimating kW reductions
will be determined from the current load profile for each Facility.
The customer baseline load profile and strategy for accomplishing
peak load reductions must be clearly delineated in the Technical Assessment
(see Appendix D).
The integrated program consists of four components: (See Section
II, Program Requirements for a complete description of eligibility
requirements and program administration.)
Permanent Demand Reduction Efforts (PDRE) result in reduced
peak demand, through the installation of equipment that provides long-term
(expected to be in place and operational for at least five years),
overall system coincident peak demand reduction. Capital improvements
requiring design and installation periods of greater than 8 months
are strongly encouraged to investigate the Commercial/Industrial Performance
Program, and/or other NYSERDA funded programs.
Load Curtailment/Shifting (LC/S) results in reduced peak demand
either in response to an electric capacity shortfall, or defined price
signal. Each participating Facility must participate in a New York
Independent System Operator (NYISO) Demand Response Program (DRP),
an Acceptable Load Serving Entity (LSE) Load Management Program, or
a Time of Use (TOU) or Real Time Pricing (RTP) Program.
Dispatchable Emergency Generator Initiatives (DEGI) result
in reduced peak demand, at times of capacity shortfall, by enabling
owners of existing emergency/backup generators in the Con Edison service
territory to offload all, or a percentage of their electric capacity
requirements to their own generators, in response to a communication
from the New York Independent System Operator's Emergency Demand Response
Program (EDRP) or a Transmission Owner Load Management Program. Except
for specific replacement provisions established herein, the purchase
or installation of new generation equipment is ineligible for incentives
under this program.
Interval Meters (IM) result in reduced peak demand through
the purchase and installation of Interval Meters to enable participation
in load reduction programs such as the NYISO's demand response programs,
and/or an Acceptable LSE Load Management Program, including a TOU
or RTP program.
Eligible Contractors are encouraged to investigate other New
York Energy $martSM programs, including the Commercial/Industrial
Performance Program, the New Construction Program, Smart Equipment
Choices, Technical Assistance, Distributed Generation/Combined Heat
& Power (DG/CHP) program, and the Loan Program. These programs
offer incentives for the purchase and installation of energy efficient
equipment. See NYSERDA's website (www.nyserda.org) for more information
on each of these programs.
B. AVAILABLE FUNDS
NYSERDA has up to $11 million available for incentives to Contractors
under this solicitation. The program terms offered through this PON
are effective as of October 2, 2002. Section I.C.(3). addresses program
incentive caps by Contractor, Facility and Project.
Applications will be processed on a first-come, first-served basis
until all funds are committed, or through October 31, 2003, whichever
is earlier. Contractors awarded an incentive will be issued one or
more Purchase Orders from NYSERDA.
C. INCENTIVES
TABLE 1 - Project Incentive Caps 1, 2
| PDRE |
LC/S |
DEGI |
IM |
|
Con Edison
Service Territory
|
Non-
Con Edison
Service Territory
|
Con Edison
Service
Territory
|
Non-
Con Edison
Service Territory
|
Con Edison
Service Territory only
|
Statewide
PSC Approved
|
Statewide
NYISO Compliant
|
|
$475/kW
|
$175/kW
|
$175/kW
|
$55/kW
|
$125/kW
|
$2,500 per meter 3
|
$1,200 per meter 3
|
1 NOTE: Contractors will be reimbursed the lesser of 70% of the Eligible
Project Costs or the incentive caps set forth in Table 1. The Facility
owner/operator must contribute no less than 30% of Eligible Project
Costs.
2 NYSERDA reserves the right to increase program incentives within
the Con Edison service territory.
3 NOTE: New York State Public Service Commission Approved Interval
Meters will be reimbursed the lesser of 70% of Eligible Project Costs
or $2,500/meter, NYISO Compliant Interval Meters will be reimbursed
the lesser of 70% of Eligible Project Costs or $1,200/meter. Field
Verification is required for certain Interval Meter only Projects.
1. Reimbursement Incentives
Eligible Facilities must contribute to the SBC. In the event the
customer pays the SBC on less than 50 percent of the total annual
electric consumption (kWh) at the Facility, the incentive will be
prorated accordingly.
The Contractor will be reimbursed the lesser of 70% of the Eligible
Project Costs or the incentive caps set forth in Table 1. The Facility
owner/operator must contribute no less than 30% of Eligible Project
Costs and take ownership of all measures funded under PON 733-02.
NYSERDA reserves the right to require documentation from the Contractor
to demonstrate the Facility owner/operator minimum payment requirement.
NYSERDA reserves the right to require canceled checks to verify
that Eligible Project Costs have been incurred.
The final incentive payment will be determined, per PON 733-02
and the Purchase Order (PO), including Exhibit A, based on an approved
Technical Assessment (developed by the Contractor) and Field Verification
of equipment installed and operational, as outlined in the Technical
Assessment, and appropriate Facility specific invoices. These incentives
may be modified if the approved Technical Assessment and/or approved
Field Verification identify changes to the estimated kW demand reduction.
Ineligible Project costs include, but are not limited to, Facility
labor, or ongoing expenses such as subscription fees, software licensing
fees, service/maintenance fees, communications or internet fees,
etc.
The Contractor will be reimbursed the lesser of 70% of the Eligible
Project Costs or the incentive caps set forth in Table 1. No more
than 30% of the Eligible Project Costs shall be for project development.
Project development includes administrative costs, overhead, engineering,
marketing, development of the Technical Assessment, travel expenses,
profit, or other expenses approved by NYSERDA. No less than 70%
of the Eligible Project Costs shall be for project implementation.
Project implementation includes only direct expenses for the purchase
and installation (labor and material costs) of equipment at the
Facility, such as on-site operation and maintenance improvements,
energy management system upgrades, advanced metering, Direct Load
Control (DLC) technologies, disposal fees, or other expenses approved
by NYSERDA. Eligible Project Costs must be specifically itemized
for each Facility, including materials and equipment expenses, staff
names and titles identified, billable hourly rate, tasks performed,
and hours applied to specific tasks. Invoice items must be specifically
identified as project development expenses or project implementation
expenses. All invoices must include a signed invoice cover sheet,
included in Appendix F. Invoice requirements apply to all invoices
submitted, including Contractor invoices and subcontractor invoices.
NYSERDA will inform all Facilities of incentives provided to their
Contractor.
2. Aggregation Incentive
Contractors who aggregate greater than 10 MW of Field Verified
demand reduction, under PON 733-02, are eligible for a $100,000
aggregation incentive. Upon receipt of applications from a single
Contractor equaling or exceeding 10 MW of demand reduction, NYSERDA
will issue a purchase order to the Contractor for $100,000. Aggregation
incentives will be paid in two installments: 50% after Field Verification,
and 50% when the Contractor verifies, by way of final report(s)
to NYSERDA, that no less than 80% of demand reductions have been
achieved as confirmed by the final report(s) submitted to NYSERDA.
Final reports to NYSERDA must use the same demand reduction calculation
methodology as required by the specific NYISO DRP. Technical Assessments,
Field Verifications, and final reports must confirm that a single
Contractor has completed Projects resulting in greater than 10 MW
of demand reduction. Demand reductions resulting solely from the
installation of Interval Meters are not eligible to receive the
aggregation incentive.
The PON 733-02 aggregation incentive is to support the development
and implementation of demand response projects that deliver NEW
demand response resources. The Aggregation Incentive is limited
to technology and infrastructure improvement-based demand response
Projects - not behavior-based demand response Projects. The Aggregation
Incentive is limited to one award per NYSERDA PON 733 -02 Contractor.
The aggregation incentive is to deliver new demand response resources
at a diversity of Facilities, through a diversity of Contractors,
to foster a vibrant and competitive demand response market. To this
end, we will closely monitor the distribution of Aggregation Incentive
awards, and the Facilities, Contractors and CSPs involved. Should
we see a concentration, rather than a diversity, the program may
be adjusted accordingly.
3. Program Incentive Caps
(a.) Unless otherwise approved by NYSERDA, the total incentive per
Contractor under this Program will not exceed 20% of the total funding
for this solicitation (initial Contractor cap - $2.2 million), excluding
the Aggregation Incentive. (b.) Unless otherwise approved by NYSERDA,
the total incentive per Facility for measures under this Program will
not exceed 5% of the total funding for this solicitation (initial
Facility cap - $550,000). (c.) Program incentives for the NYISO Day
Ahead Demand Response Program (DADRP) and Time of Use or Real Time
Pricing Projects are limited to $1.5 million. (d.) The total incentive
for the DEGI component of the program will not exceed 20% of the total
funding of this solicitation. (e.) Contractor and/or Facility caps
may be adjusted based on program activity and funding resources.
D. LIMITATIONS
Eligible Project Costs must be incurred between October 2, 2002 and
March 31, 2004. Measures for which expenses have been incurred prior
to October 2, 2002 are ineligible for incentives. All Purchase Orders
expire on April 30, 2004, unless the Contractor provides written justification,
by January 30, 2004, acceptable to NYSERDA, for the delay in completing
the Project. NYSERDA will not make payment on an expired Purchase
Order. Incentives awarded under PON 733-02 cannot pay for measures
funded under other NYSERDA programs. Single family residences are
ineligible, except for select aggregated Facilities. Demonstration
projects and/or new unproven technologies are ineligible.
Participants that received a Purchase Order which expired under
PON 620-01 (Peak-load Reduction Program), but did not implement the
funded demand reduction measures nor receive funds for the demand
reduction measures under other NYSERDA programs, may apply to PON
733-02.
The Contractor is responsible for obtaining all required local,
state, and federal permits, and is responsible for complying with
all applicable building, health, environmental, and safety codes.
E. APPLICATION PROCESS
The application process begins when the Applicant submits a completed
application to NYSERDA (see Appendix A and Appendix B1-B4), on behalf
of one or more Facilities. All applications must be submitted by an
Eligible Contractor. For aggregated Projects, only one Appendix A
per submitted aggregation is required, although one or more Appendix
B must be completed for each Facility. Appendix B must describe each
Project for a particular Facility and indicate an estimated summer
peak kW demand reduction for each Facility. The Applicant Checklist
is located in Appendix A, Facility Data Sheets are located in Appendices
B1-B4, sample Purchase Orders are located in Appendix C, a Technical
Assessment outline is attached as Appendix D, a Contractor Checklist
is located in Appendix E, and an Invoice Cover Sheet is located in
Appendix F.
F. DEFINITIONS
Acceptable LSE Load Management Program - load management programs,
such as TOU or RTP, or NYISO's DRPs, intended to motivate electric
consumers to reduce on-peak electric demands. Programs must be offered
by Load Serving Entities, or Transmission Owners, and must be acceptable
to NYSERDA, and/or the Public Service Commission.
Applicant - Any entity, proposing a Project at an SBC-eligible Facility,
submitting an application under this solicitation.
B20 - a blended Biodiesel mixture consisting of 20% (by volume)
Biodiesel and 80% (by volume) petro-diesel fuel.
Biodiesel - A fuel consisting of long-chain fatty acid alkyl esters
made from renewable vegetable oils, recycled cooking greases, or animal
fats that meets ASTM standard D6751with properties similar to No.2
petroleum diesel fuel.
Contractor - Any Applicant, proposing/developing a Project at an SBC-eligible
Facility, that is awarded a Purchase Order under this solicitation.
Curtailment Service Provider (CSP) - A CSP is a load aggregator,
energy service company (ESCO), or electric utility authorized, but
not required, to provide load reductions under the New York Independent
System Operator's Emergency Demand Response Program (NYISO's EDRP),
or its Day Ahead Demand Response Program (DADRP).
Direct Load Control (DLC) - A load reduction strategy that can interrupt
consumer load or modify settings or schedules of equipment at the
time of a NYISO or LSE peak demand period, or in conjunction with
Time of Use or Real Time Pricing programs. Equipment must be controlled
for an aggregated set of Facilities, by way of remote, centrally dispatched
communication/control. Notwithstanding any other provisions of this
solicitation, DLC Projects are eligible for all building types.
Eligible Contractor - An Eligible Contractor must be capable of,
or must retain services capable of developing a summer peak demand
reduction Project, and implementing all necessary measures. Eligible
Contractors include individual building owners or operators, lease
holders, energy services companies, load serving entities, transmission
and/or distribution utilities, CSPs, equipment installers, engineering
firms, and energy management firms. See Sections VII. NON-COMPLIANCE
for additional eligibility requirements.
Eligible Project Costs - Incurred costs associated with the development
and implementation of the measures necessary to achieve the Project's
objectives, in accordance with the Purchase Order, Exhibits A and
B, and as outlined in this Program Opportunity Notice. Ineligible
Project costs include Facility labor, or ongoing expenses such as
subscription fees, software licensing fees, service/maintenance fees,
communications/internet fees, etc.
Facility - The location where the Project is proposed and implemented.
To be eligible for this program, a Facility must pay into the System
Benefits Charge.
Field Verification - The final site visit, performed by the NYSERDA
Consultant, to verify that the measures identified in the Technical
Assessment have been installed, are operational, and are capable of
delivering the kW reduction as documented in the Technical Assessment.
Interval Meters - The Interval Meters component provides two distinct
functions: meters that capture energy use information more complex
than mere tracking of accumulated flow; and communication systems
that capture, store and communicate energy use information.
PSC Approved Interval Meters - Interval Meter approved by the
New York State Public Service Commission, and installed by a Meter
Service Provider, in a configuration compliant with the New York
State Public Service Commission to be used for billing purposes.
Interval Meters installed under this component must be capable of;
1) Supporting Time of Use and Real Time Pricing rate plans and 2)
providing read-only access of revenue grade data to the Facility
or a designated agent of the Facility.
NYISO Compliant Interval Meters - Interval Meter that is compliant
with the NYISO regulations, as they pertain to NYISO's DRP.
Load Serving Entity (LSE) - Any entity authorized or required by
law, regulatory authorization or requirement, agreement, or contractual
obligation to supply energy, capacity and/or ancillary services to
retail end users located within the New York Control Area (NYCA),
including NYISO direct customers. For purposes of this PON, eligible
LSE's must demonstrate the presence of a New York State office.
Meter Service Provider - Entities approved by the New York State
Public Service Commission to install meters to be used for billing
purposes in New York State.
NYISO - New York Independent System Operator.*
NYISO's EDRP - New York Independent System Operator's Emergency Demand
Response Program.*
NYISO's ICAP - New York Independent System Operator's Installed
Capacity Program.*
NYISO's DRP - New York Independent System Operator's Demand Response
Programs, including the Day Ahead Demand Response Program (DADRP),
Emergency Demand Response Program (EDRP), Installed Capacity Program
(ICAP), Special Case Resources (SCR), Unforced Capacity Program (UCAP),
and virtual bidding.*
NYSERDA Consultant - An engineering consultant under contract to
NYSERDA to provide technical support and field verification services
for this program.
Project - The implementation of demand reduction measure(s) at a
Facility by an Eligible Contractor.
Qualifying Generators - All customer owned/operated generators,
model year 1995 or newer; or all model year 1994 and older generators
that demonstrate either by generator specific manufacturer's data
or through emissions testing, that NOx emissions do not exceed 35
pounds per megawatt-hour (lb/MWh). Emissions testing methods for test
and tune purposes should be conducted consistent with industry established
protocols (such as the American Society for Testing and Materials
[ASTM] D6522-00) and applicable DEC regulations.
Real Time Pricing (RTP) - A market-based electric rate alternative
that regularly informs consumers of dynamic pricing, typically reflecting
periods of scarcity with increased prices and periods of surplus with
reduced prices.
Summer Peak Demand Reduction Period - May 1 to October 31, during
the hours of 11:00 AM to 7:00 PM.
Technical Assessment (TA) - A site specific, engineering or feasibility
study describing peak load Permanent Demand Reduction Efforts, Load
Curtailment/Shifting, and/or Dispatchable Emergency Generator Initiatives,
the methodology for determining kW demand reduction and kWh savings,
a summary of pre- and post- installation coincident kW demand and
kWh use, and measure costs (see Appendix D).
Time of Use Pricing (TOU) - An electric rate alternative that offers
pre-determined, time sensitive rates for defined periods that reflect
the costs of providing the energy and capacity to the customer.
Transmission Owner - The public utility or authority (or its designated
agent) that owns facilities used for the transmission of energy in
interstate commerce and provides transmission service under a New
York PSC approved tariff.
Ultra Low-Sulfur Fuel - Distillate fuel oil having a sulfur content
less than, or equal to, 30 parts per million by weight.
*NOTE: For more information about programs offered by the New York
Independent System Operator, visit the NYISO website at www.nyiso.com
II. PROGRAM REQUIREMENTS
A. PERMANENT DEMAND REDUCTION EFFORTS (PDRE)
1. Eligibility
- Measures implemented under this component are to be installed
and operational at the Facility for at least 5 years.
- Measures must be operational and reduce coincident demand at a
Facility during the entire Summer Peak Demand Reduction Period,
consistent with the measures' normal operating schedules.
- Measures must be activated in an automatic mode as an integrated
function of the operation of the building systems or equipment.
- For any project based on control or electric generation strategies
(e.g. PV), Contractors must provide a more extensive and detailed
TA that assures a higher level of confidence that proposed electric
demand reductions are both achievable and persistent.
- Lighting measures must be hard-wired installations. Screw-in lamps
and/or screw-in ballasts are ineligible for funding under this solicitation.
Power quality and power factor improvements are ineligible for funding
under this solicitation.
- Fuel cells and Photovoltaic (PV) installations are eligible for
funding under this component of this solicitation.
- Demand reductions resulting from the installation of the following
fossil-fuel fired generators are ineligible for funding under this
component of this solicitation: microturbines, internal combustion
engine-driven electric generation, and combined heat and power equipment.
PDRE measures resulting in increased Facility emissions will be
considered on a case by case basis.
2. Minimum Project Size
The minimum Project size is 40 kW, although Projects resulting
in demand reductions of less than 40 kW will be considered on a
case-by-case exception basis.
3. Incentives
- Eligible Project Costs include engineering services, procurement
and installation of capital equipment, metering equipment, or other
NYSERDA approved expenses incurred to permanently reduce summer
peak demand.
- Capital equipment includes equipment improvements that result
in reduced electric demand, such as heating, ventilation and air-conditioning
(HVAC) equipment, lighting equipment, controls for HVAC and lighting
equipment, motors, PV, and select motor drives.
For Projects in the Con Edison Service Territory:
The lesser of 70% of Eligible Project Costs or $475/kW of summer
peak demand reduction for measures installed, operational, and Field
Verified on or before March 31, 2004.
For Projects Outside the Con Edison Service Territory:
The lesser of 70% of Eligible Project Costs or $175/kW of summer
peak demand reduction for measures installed, operational, and
Field Verified on or before March 31, 2004.
B. LOAD CURTAILMENT/SHIFTING (LC/S)
1. Eligibility
- Contractors must show registration or proof of each Facility's
participation, for no less than one entire Summer Peak Demand Reduction
Period, in a NYISO DRP, an Acceptable LSE Load Management Program,
or a TOU or RTP program, and that each Facility is willing and technically
capable of receiving, and responding to a communication, or price
signal.
- Each LC/S Project, must have the willingness and technical capability
to curtail electric load at least 12 times, for a duration of not
less than four hours per curtailment, for a total of no less than
48 hours over the Summer Peak Demand Reduction Period.
- Facilities participating only in TOU or RTP programs must control
load in an automatic fashion to be eligible for funding under Load
Curtailment/Shifting.
- Non-aggregated residential customers are ineligible to receive
funding under Load Curtailment/Shifting.
- The Project must be comprised of installed measures that enable
curtailing or shifting electric use during the entire Summer Peak
Demand Reduction Period.
- Demand reductions resulting from the installation of new microturbines,
generation, or co-generation equipment are ineligible.
2. Minimum Project Size
Notwithstanding DLC Projects, the minimum proposed demand reduction
Project shall be at least 100 kW. DLC projects must be aggregated
to 100 kW, but have no Facility minimum.
3. Incentives
Incentives will be paid to the Contractor regardless of whether
or not there is a communication from NYISO or LSE during the Summer
Peak Demand Reduction Period.
-
Eligible Project Costs include engineering services, procurement
and installation of capital equipment, metering equipment, training
of Facility staff, and development of a curtailment plan. Capital
equipment includes equipment that reduces electric demand, such
as controls and improvements to heating, ventilation and air-conditioning
(HVAC), lighting, process loads, motors, and motor drives. Other
related expenses to develop and implement projects will be considered
on a case-by-case basis.
- The expenses for closing of a Facility, loss of revenue due to
the closing of a Facility as a Load Curtailment/Shifting measure,
or additional staff costs due to shifting operations to off-peak
hours are ineligible for an incentive.
The NYSERDA funded kW demand reduction shall not exceed that which
is registered with the NYISO or an Acceptable LSE Load Management
Program.
For Projects in the Con Edison Service Territory:
The lesser of 70% of Eligible Project Costs or $175/kW of summer
load curtailment for measures installed, operational, and Field
Verified on or before March 31, 2004.
For Projects Outside the Con Edison Service Territory:
The lesser of 70% of Eligible Project Costs or $55/kW of summer
load curtailment for measures installed, operational, and Field
Verified on or before March 31, 2004.
C. DISPATCHABLE EMERGENCY GENERATOR INITIATIVES (DEGI)
1. Eligibility
- Qualifying Generators, within the Con Edison service territory
only, are eligible for incentives under the DEGI component. Contractors
must show registration or proof of each Facility's participation,
for no less than one entire Summer Peak Demand Reduction Period,
in the NYISO's EDRP or a Transmission Owner Load Management Program.
- Facilities must have the willingness and technical capability
to operate during the entire Summer Peak Demand Reduction Period,
but need only operate when it receives a communication from the
NYISO or a Transmission Owner. Each NYSERDA approved DEGI Project
must have the capability to operate at least 12 times, for a duration
of not less than four hours, for a total of no less than 48 hours,
and no more than 200 hours, over the Summer Peak Demand Reduction
Period.
- The project must be comprised of installed measures that enable
emergency generators to be operated solely in response to a communication
from NYISO's EDRP or a Transmission Owner Load Management Program.
- Except for the specific replacement provisions covered below,
the purchase or installation of new generation equipment is ineligible.
- Eligibility of replacement units is limited to emergency or backup
generators within the Con-Edison service territory, that meet emissions
criteria for both the new replacements as well as the units displaced.
Replacement units must document manufacturer specific equipment
NOx emission rates equal to or less than 18 lbs/MWh. In addition,
replacement units must emit less than ½ the NOx emissions
(lbs/MWh) of the unit being displaced. Replacement units must document
manufacturer specific equipment PM10 emissions rates equal to or
less than 0.70 lbs/MWh.
- The maximum electric output of the new replacement unit(s) must
not exceed 125% of the existing unit(s). Existing units must be
removed and de-manufactured or scrapped, and the Contractor must
provide proof that this requirement has been met.
- Contractors and Facilities should be aware that DEC is currently
in the process of revising regulations applicable to distributed
generation resources. Generators that meet the requirements of this
solicitation are not assured that such units will meet future regulatory
requirements.
- Eligible Contractors may modify or tune emergency generators in
order to meet emission requirements of a Qualifying Generator. Generator
specific manufacturer's data is considered adequate documentation
for the Contractor to demonstrate that the equipment meets the NOx
threshold requirement.
- Contractors must self certify that all Facilities with generators
have applied for or received all required State and local permits
or registrations necessary to operate the generators in a demand
response program.
2. Minimum Project Size
The minimum Project size is 200 kW.
3. Incentives
Incentives will be paid to the Contractor regardless of whether
or not there is a communication from NYISO's EDRP or a Transmission
Owner Load Management Program during the Summer Peak Demand Reduction
Period.
- Eligible Project Costs include engineering services, procurement
and installation of metering equipment, testing and tuning of emergency
generators, improvements to reduce environmental impacts, incremental
cost of Ultra Low-Sulfur Fuel or Biodiesel (a blend no less than
B20), rewiring circuits, installation of transfer switchgear, environmental
permitting, selective use of catalytic reduction technologies, stack
modifications, operational improvements, implementation of natural
gas dual-fuel options, and eligible replacement units. Other related
costs will be considered on a case-by-case basis.
- The NYSERDA funded demand reduction shall not exceed that which
is registered with the NYISO's EDRP or a Transmission Owner Load
Management Program.
For Projects in the Con Edison Service Territory ONLY:
The lesser of 70% of Eligible Project Costs or $125/kW of dispatchable
emergency generation for Qualifying Generators installed, operational,
and Field Verified on or before March 31, 2004.
4. Required Mitigation Measures
To further mitigate environmental impacts of this program, NYSERDA
will purchase and retire NOx allowances equal to twice the total
calculated NOx emissions generated from this component. NOx emissions
will be based on the actual hours of operation of the emergency
generators and an average NOx emission rate of 35 lb/MWh for all
participants of this component. The allowances will be purchased
in one block at the end of the Summer Peak Demand Reduction Period.
D. INTERVAL METERS (IM)
1. Eligibility
- Interval Meters are to be operational at the Facility(ies) for
at least two years.
- Interval Meters are to be used to enable/verify kW demand reductions
for NYISO DRP, an Acceptable LSE Load Management Program, or TOU
or RTP program for non-residential customers. Interval Meters to
be used for other purposes must receive prior approval by NYSERDA.
- Interval Meters installed at points other than the main electrical
feed(s) or generators must provide a Technical Assessment and must
receive prior approval from NYSERDA.
- NYSERDA must be provided read only access, for a minimum period
of two years, to all Interval Meters funded by PON 733-02.
2. Minimum Project Size
The minimum Project size is 40 kW, but any Interval Meter enabling
less than a 40 kW demand reduction will be considered on a case-by-case
exception basis.
3. Incentives
-
Contractors must provide proof of participation, for no less
than one entire Summer Peak Demand Reduction Period, by each Facility
in a NYISO DRP, an Acceptable LSE Load Management Program, or
TOU or RTP program.
- Eligible Project Costs are limited to the purchase and installation
of individual metering systems that are connected to the following
in accordance with PSC regulations: 1) main electrical feeds (i.e.
utility service entrance or master meter point), 2) equipment that
can reasonably be curtailed, or 3) emergency/backup generator equipment.
For Interval Meters Installed Statewide:
PSC Approved Interval Meters are eligible for the lesser of 70%
of Eligible Project Costs or $2,500/meter. Such Interval Meters
must be approved by the New York State Public Service Commission,
and installed by a Meter Service Provider, in a configuration compliant
with the New York State Public Service Commission to be used for
billing purposes. Interval Meters installed under this component
must be capable of; 1) Supporting Time of Use and Real Time Pricing
rate plans and 2) providing read-only access of revenue grade data
to the Facility or a designated agent of the Facility.
NYISO Compliant Interval Meters are eligible for the lesser of 70%
of Eligible Project Costs or $1,200/meter. Such Interval Meters
must be compliant with the NYISO regulations, as they pertain to
NYISO's DRP.
III. PROJECT IMPLEMENTATION PROCESS
A. PDRE, LC/S, AND DEGI PROJECTS
Unless noted otherwise, each of the following steps must be completed
to receive payment. A checklist is provided in Appendix E.
1. Eligible Contractor submits application to NYSERDA on or before
October 31, 2003. If the completed application meets all program criteria,
NYSERDA will encumber funds for that Project, and issue a Purchase
Order.
2. Once a Purchase Order is issued, a NYSERDA Consultant will be
assigned to the Contractor's Project at no cost to the Contractor.
The Consultant is assigned to the Project to review demand reduction
measures identified and recommended in the Technical Assessment and
to complete a Field Verification. The NYSERDA Consultant will contact
the Contractor.
3. The Contractor must submit a completed Technical Assessment to
their assigned NYSERDA Consultant for a review of technical accuracy
within 70 days of receipt of the Purchase Order, otherwise, the Purchase
Order may be voided. The Technical Assessment provides appropriate
technical documentation and backup data to support the estimated kW
demand reduction provided in Appendix B of the application. See Appendix
D for Technical Assessment Outlines.
4. The NYSERDA Consultant reviews the Technical Assessment for technical
accuracy and provides recommendations to the Contractor concerning
the proposed kW savings within ten (10) business days of receipt of
the Technical Assessment. It is the Contractor's responsibility to
address and resolve all issues raised by the NYSERDA Consultant regarding
the technical accuracy and feasability of the Technical Assessment.
5. The NYSERDA Consultant provides its recommendations to NYSERDA.
NYSERDA will notify the Contractor whether or not the Technical Assessment
is approved by NYSERDA. If approved, NYSERDA will issue a notice-to-proceed,
stating the Technical Assessment approved kW demand reduction. Any
Contractor proceeding with implementation of the Project before receiving
a notice-to-proceed from NYSERDA does so at its own risk.
6. Upon receipt of the notice-to-proceed, the Contractor shall proceed
to implement measures, as specified in the approved Technical Assessment.
7. Upon Project completion, the Contractor must contact their assigned
NYSERDA Consultant to schedule the post-installation Field Verification.
Once the Contractor notifies the NYSERDA Consultant of Project completion,
the NYSERDA Consultant must conduct a post-installation Field Verification
visit.
8. Upon completion of the Field Verification, the NYSERDA Consultant
will provide written documentation to NYSERDA summarizing its technical
review of the Project installation and providing a recommended final
kW of summer peak demand reduction. If approved by NYSERDA, a notice-to-invoice
will be sent to the Contractor, verifying that completed measures
have been approved and stating the final adjusted kW demand reduction
based on the Field Verification and actual operation of the equipment.
If the kW summer peak demand reduction from the Field Verification
is greater than the amount estimated in Appendix B of the application,
the Purchase Order will be amended to reflect the increased incentive,
provided sufficient funds still exist in the program.
9. Upon receipt of complete invoices and documentation, the Contractor
receives the incentive. Deliverables required in order to receive
the incentive are: 1) Appendix F accompanied by copies of Facility
specific vendor invoices and documentation to verify project development
and project implementation, 2) the notice-to-proceed from NYSERDA
verifying approval of the Technical Assessment, 3) the notice-to-invoice
from NYSERDA verifying post installation/operation approval of the
summer peak demand reduction measures, 4) documentation from the Contractor
demonstrating that the Facility owner/operator has contributed the
required minimum payment of no less than 30% of Eligible Project Costs,
and 5) for Load Curtailment/Shifting, Dispatchable Emergency Generation
Initiative, and Interval Meter Projects, proof of registration in
one or more of the acceptable demand reduction programs. NYSERDA reserves
the right to require additional deliverable documentation as necessary.
10. Contractor submits all necessary reports to NYSERDA.
B. IM PROJECTS
Each of the following steps must be completed to receive payment.
A checklist is provided in Appendix E.
1. Eligible Contractor submits application to NYSERDA.
2. Once a Purchase Order is issued, the Contractor shall proceed
to have the Interval Meters installed and made operational.
3. The Contractor may submit an invoice after all meters within
a Purchase Order are installed and made operational.
4. Interval Meters installed at points other than the main electrical
feed(s) or generators must provide a Technical Assessment and must
receive prior approval from NYSERDA.
5. Upon receipt of complete invoices and documentation, the Contractor
receives the incentive. Deliverables required in order to receive
the incentive are: 1) A description of the specific metering improvements
and their locations and installation points, 2) Appendix F accompanied
by copies of Facility specific vendor invoices, and 3) proof of installation
and program participation in a NYISO DRP, an Acceptable LSE Load Management
Program, or other load reduction programs offered by LSEs, including
Real Time or Time of Use pricing.
6. Contractor submits all necessary reports to NYSERDA.
IV. METERING REQUIREMENTS
All Projects participating in the LC/S and DEGI must have appropriate
metering technology installed. All projects with 100kW or more of
summer peak demand reductions are required to permanently install
and make operational Interval Meters. Metering equipment meeting the
definition of Interval Meters in this PON will be deemed adequate.
Hourly metered data must be archived for two years, and be made available
to NYSERDA upon request, in appropriate electronic format. If this
metered data is provided via website, the data must be made available
to NYSERDA in read only format. Metered data must be made available
to NYSERDA for a two-year period. Contractors shall obtain written
consent from their clients to permit NYSERDA access to this data.
This data will be used only for internal analysis, future program
development purposes, and verification of demand reductions. All data
shall be protected to the fullest extent possible under the New York
State Freedom of Information Law.
V. REPORTING REQUIREMENTS
A. INTERMEDIATE REPORTS
For the LC/S, DEGI, and IM components, each time a Contractor
or Facility is required to submit a report to the NYISO or an Acceptable
LSE Load Management Program for incentive payments as part of a load
management program, a copy of that report shall be sent to the Peak-load
Reduction Program at NYSERDA within five (5) business days of the
submission of the report to the NYISO or an Acceptable LSE Load Management
Program.
B. FINAL REPORTS
By April 30, 2004, each Contractor participating in this Program shall
submit a final report to NYSERDA detailing:
1. Total kW contracted for this Program,
2. Actual system coincident peak demand reductions realized,
3. Number and duration of each of NYISO's DRP or LSE Load Management
Program communications (for Load Curtailment/Shifting and Dispatchable
Emergency Generator Initiatives only),
4. Actual demand reduction (kW) achieved in response to each NYISO
DRP or LSE Load Management Program communication (for LC/S, DEGI and
IM measures only).
5. The technical approach to secure the kW reductions. Explain any
case(s) in which kW reductions either outperformed (greater than 120%)
or underperformed (less than 80%) pledged kW reduction when called
for by a NYISO DRP or LSE Load Management Program.
Failure to provide all required reports will render the Contractor
ineligible for NYSERDA's Peak-load Reduction Program in the current
year (2003) as well as for the anticipated 2004 program.
VI. PROGRAM EVALUATION
NYSERDA requires Contractors who participate in PON 733-02 to respond
to surveys and to provide feedback through program evaluations to
assess program effectiveness. Failure to cooperate with evaluations
may result in ineligibility for NYSERDA programs.
VII. NON-COMPLIANCE
Contractors may be deemed to be in non-compliance with this program
for any of the following: 1) Contractors fail to meet at least 80%
of demand reductions or dispatched emergency generation, as contracted
by the final NYSERDA incentive, 2) Contractors fail to submit the
final report as required in Section V. REPORTING REQUIREMENTS of this
solicitation, 3) Contractors fail to submit copies of NYISO DRP or
an Acceptable LSE Load Management Program report to NYSERDA as required
in Section V. REPORTING REQUIREMENTS of this solicitation, or 4) Contractors
that have not complied with program requirements in a timely manner.
Contractors deemed to be in non-compliance shall have their PO cancelled
and shall become ineligible for any or all future Peak-load Reduction
Programs.
VIII. DISCLAIMER
NYSERDA's receipt and acceptance of the Technical Assessment shall
not constitute any representation by NYSERDA as to the economic or
technical feasibility, operational capability, or reliability of the
information contained in the Technical Assessment. NYSERDA's payment
of the incentive to the Contractor shall in no way represent an endorsement
by NYSERDA of any findings or recommendations contained in such TA.
IX. APPLICATION REQUIREMENTS
Applicants must fill out the Applicant Checklist (Appendix A) and
the appropriate Facility Data Sheet(s) (Appendix B(s)), completely,
leaving no blank information. This information will be used to determine
the incentive award. For ease of use, the application package is also
available on NYSERDA's website. Paper copies of application forms
and the application checklist must contain an original signature.
Applications aggregating two or more Facilities must list each Facility
separately on the application form, identifying the estimated summer
peak demand reduction expected at each Facility. A Facility with multiple
buildings may be aggregated into one Facility Data Sheet.
X. GENERAL CONDITIONS
Proprietary Information - Careful consideration should be given before
confidential information is submitted to NYSERDA as part of your proposal.
Review should include whether it is critical for evaluating a proposal,
and whether general, non-confidential information, may be adequate
for review purposes.
The NYS Freedom of Information Law, Public Officers law, Article
6, provides for public access to information NYSERDA possesses. Public
Officers Law, Section 87(d)(2) provides for exceptions to disclosure
for records or portions thereof that "are trade secrets or are
submitted to an agency by a commercial enterprise or derived from
information obtained from a commercial enterprise and which if disclosed
would cause substantial injury to the competitive position
of the subject enterprise." Information submitted to NYSERDA
that the proposer wishes to have treated as proprietary, and confidential
trade secret information, should be identified and labeled "Confidential"
or "Proprietary" on each page at the time of disclosure.
This information should include a written request to except it from
disclosure, including a written statement of the reasons why the information
should be excepted. See Public Officers Law, Section 89(5) and the
procedures set forth in 21 NYCRR Part 501.
Omnibus Procurement Act of 1992 - It is the policy of New
York State to maximize opportunities for the participation of New
York State business enterprises, including minority- and women-owned
business enterprises, as bidders, subcontractors, and suppliers on
its procurement Agreements.
Information on the availability of New York subcontractors and suppliers
is available from:
Empire State Development
Division For Small Business
30 South Pearl Street
Albany, NY 12245
A directory of certified minority- and women-owned business enterprises
is available from:
Empire State Development
Minority and Women's Business Development Division
30 South Pearl Street
Albany, NY 12245
Contract Award - NYSERDA anticipates making multiple, as
it applies to this solicitation, award(s) under this solicitation.
It may award a contract based on initial applications without discussion,
or following limited discussion or negotiations. Each offer should
be submitted using the most favorable cost and technical terms. NYSERDA
may request additional data or material to support applications. NYSERDA
will use the Sample Agreement to contract successful proposals.
Limitation - This solicitation does not commit NYSERDA to
award a contract, pay any costs incurred in preparing a proposal,
or to procure or contract for services or supplies. NYSERDA reserves
the right to accept or reject any or all proposals received, to negotiate
with all qualified sources, or to cancel in part or in its entirety
the solicitation when it is in NYSERDA's best interest.
Disclosure Requirement - The proposer shall disclose any indictment
for any alleged felony, or any conviction for a felony within the
past five years, under the laws of the United States or any state
or territory of the United States, and shall describe circumstances
for each. When a proposer is an association, partnership, corporation,
or other organization, this disclosure requirement includes the organization
and its officers, partners, and directors or members of any similarly
governing body. If an indictment or conviction should come to the
attention of NYSERDA after the award of a contract, NYSERDA may exercise
its stop-work right pending further investigation, or terminate the
agreement; the contractor may be subject to penalties for violation
of any law which may apply in the particular circumstances. Proposers
must also disclose if they have ever been debarred or suspended by
any agency of the U.S. Government or the New York State Department
of Labor.
| Attachments: |
| Appendix A - Applicant Checklist |
| Appendix B1- Permanent Demand Reduction Efforts
Facility Data Sheet |
| Appendix B2 - Short-Duration Load Curtailment Measures
Facility Data Sheet |
| Appendix B3 - Dispatchable Emergency Generator Initiatives
- Facility Data Sheet |
| Appendix B4 - Interval Meters - Facility Data Sheet |
| Appendix C - Sample Purchase Orders |
| Appendix D - Technical Assessment Outlines |
| Appendix E - Contractor Checklist |
| Appendix F - Invoice Cover Sheet |
|
|