This Solicitation is Now Closed -
see 733
 |
Peak-Load Reduction Program
Program Opportunity Notice (PON)
No. 620-01
|
$10.5 million available for summer peak demand reduction
measures
|
Applications accepted on a first-come,
first-served basis through October 1, 2002*.
|
Significant Changes effective 7/29/02
Major changes include, but are not limited to: application deadline
being extended to October 1, 2002; extending the milestone date for
measurement and verification of certain measures to December 31, 2002;
increasing the minimum demand reduction for each interval meter to
50 kW reduction (lower reductions per meter will still be considered
on a case-by-case basis); and requiring the facility owner/operators
to contribute no less than 25% of eligible project costs for certain
measures.
In addition, "Table 1 - Incentive Caps" was revised to specifically
include incentives for Short Duration Load Curtailment (SDLC) measures
and Dispatchable Emergency Generator Initiatives (DEGI) through December
31, 2002 (see table below)..
Revised Table 1 - Incentive Caps
| Installed, Operational and Field Verified* by: |
PDRE
|
SDLC
|
DEGI
|
IM
|
|
Con-Edison
Service Territory
|
Non-
Con-Edison
Service Territory
|
Con-Edison
Service Territory
|
Con-Edison
Service Territory
|
Con-Edison
Service Territory only
|
Statewide
|
| 12/31/02 |
$400/kW |
$130/kW |
$160/kW |
$50/kW |
$80/kW |
$3,000/meter |
Download a primer on NYISO Demand response
programs (It Pays to Play...Get in the Game with Three Electric
Load-Management Programs).
PON 620-01
This version has been revised as of July 29, 2002. Applicants who
submitted applications under the previous version of this solicitation
are eligible to participate pursuant to this revised PON.
The Peak-Load Reduction Program is one of the programs offered under
the umbrella of the New York Energy $martSM program.
The New York State Energy Research and Development Authority (NYSERDA),
as administrator of the New York Energy $mart program, requests
applications from Eligible Contractors to identify and implement Projects
which will result in reduced peak electric demand in New York State,
particularly New York City, for the summer of 2002 through Permanent
Demand Reduction Efforts (PDRE), Short-Duration Load Curtailment Measures
(SDLC), Dispatchable Emergency Generator Initiatives (DEGI), or Interval
Meters (IM).
Eligible Contractors are service providers capable of both developing
electric demand-reduction Projects and implementing all necessary
measures. Eligible facilities for PDRE, SDLC, and IM are electric
distribution customers of New York State's investor-owned utilities
which pay into the System Benefits Charge (SBC). Eligible facilities
for DEGI are electric distribution customers within the Con Edison
service territory which pay into the System Benefits Charge (SBC).
APPLICATION SUBMISSION: Applications must be clearly labeled
and mailed to:
Cathy Carlson, PON No. 620-01
New York State Energy Research and Development
Authority
17 Columbia Circle
Albany, New York 12203-6399
Technical questions should be directed to Christopher
Smith (518-862-1090, ext. 3360, cjs@nyserda.org)
or Peter Savio (518-862-1090, ext. 3334, or pps@nyserda.org).
Contractual questions should be directed to Mary
Sauvie (518-862-1090, ext. 3229, or mks@nyserda.org).
For questions regarding the New York Independent System Operator
(NYISO), its Emergency Demand Response Program (EDRP), or other NYISO
programs, contact Dave Lawrence at NYISO (518) 356-6084, or dlawrence@nyiso.com
________________
* Faxed proposals will not be accepted. Applications will be processed
on a first-come, first-served basis through October 1, 2002 or until
funds are fully committed, whichever comes first.
Table of Contents
I. INTRODUCTION
A. OBJECTIVE
B. AVAILABLE FUNDS
C. DEFINITIONS
D. INCENTIVES
E. ELIGIBILITY RESTRICTIONS
II. PROGRAM REQUIREMENTS
A. PERMANENT DEMAND REDUCTION EFFORTS (PDRE)
1. Eligibility
2. Incentives
3. Application Process
B. SHORT-DURATION LOAD CURTAILMENT MEASURES (SDLC)
1. Eligibility
2. Incentives
3. Minimum Project Size
4. Application Process
C. DISPATCHABLE EMERGENCY GENERATOR INITIATIVES (DEGI)
1. Eligibility
2. Incentives
3. Required Mitigation Measures
4. Minimum Project Size
5. Application Process
D. INTERVAL METERS (IM)
1. Eligibility
2. Incentives
3. Application Process
III. PROGRAM INCENTIVE CAPS
IV. PROJECT IMPLEMENTATION PROCESS
A. NON-INTERVAL METER PROJECTS
B. INTERVAL METER PROJECTS
V. METERING REQUIREMENTS
VI. REPORTING REQUIREMENTS
A. INTERMEDIATE REPORTS
B. FINAL REPORTS
VII. PROGRAM EVALUATION
VIII. NON-COMPLIANCE
IX. LIMITATIONS
X. DISCLAIMER
XI. APPLICATION REQUIREMENTS
XII. GENERAL CONDITIONS
APPENDICES
APPENDIX A - APPLICANT CHECKLIST
APPENDIX B - FACILITY DATA SHEETS
B1 Permanent Demand Reduction Efforts
B2 Short Duration Load Curtailment Measures
B3 Dispatchable Emergency Generator Initiatives
B4 Interval Meters
APPENDIX C - SAMPLE PURCHASE ORDERS
EXHIBIT A PROGRAM COMPONENT DETAILS
EXHIBIT B STANDARD TERMS AND CONDITIONS
EXHIBIT C PROMPT PAYMENT POLICY STATEMENT
APPENDIX D - SUGGESTED TECHNICAL ASSESSMENT OUTLINES
APPENDIX E - CONTRACTOR CHECKLIST
I. INTRODUCTION
A. OBJECTIVE
The objective of this PON is to establish an integrated program to
improve electric system reliability and reduce electric costs by providing
incentives that will result in significant electric coincident system
summer peak demand reduction in New York State, particularly in New
York City. Measures installed under PON 620-01 must perform as an
integrated function without compromising applicable building codes
or occupant health, comfort, or safety. All measures must meet or
exceed efficiency requirements contained in applicable codes or regulations.
For the purposes of the application, the baseline for estimating kW
reductions will be determined from the current load profile for each
Facility. The customer baseline load profile and strategy for accomplishing
peak load reductions must be further defined in the Technical Assessment.
The integrated program consists of four components:
Permanent Demand Reduction Efforts (PDRE) result in electric
load reductions which provide long-term (expected to be in place and
operational for at least 5 years), overall coincident system peak
demand reduction. Eligible measures include operation and maintenance
improvements, energy management system upgrades, metering, controls,
and scheduling improvements. Photovoltaic (PV) projects are eligible
under this component of PON 620-01. PDRE measures must be activated
in an automatic mode as an integrated function of the operation of
the building systems or equipment. Applicants are encouraged to investigate
funding opportunities under other NYSERDA-sponsored System Benefits
Charge (SBC) Programs. Capital improvements requiring design and installation
periods of greater than 6 months are strongly encouraged to investigate
PON 624-01 Commercial/Industrial Performance Program. See Section
II, Program Requirements for a complete description of eligibility
requirements and program administration. NYSERDA's incentive will
be the lesser of 75% of Eligible Project Cost or the incentives set
forth in Table 1.
Short-Duration Load Curtailment Measures (SDLC) result in reduced
peak demand at times of electric capacity shortfall in response to
an emergency communication from the New York Independent System Operator's
Demand Response Program (NYISO's DRP) or a Transmission Owner's load
reduction program. To receive an incentive under this program, the
Contractor must show for each application: registration or proof of
participation, by each participating Facility, in either the NYISO's
EDRP or a Transmission Owner's load reduction program; that each participating
Facility is an electric distribution customer of one of the State's
investor-owned utilities; and that each participating Facility pays
the System Benefits Charge. Eligible measures include load shedding,
load shifting, and peak shaving strategies. Measures such as telemetry
controls, Direct Load Controls, and radio frequency controlled strategies
are encouraged. The closing of a Facility as a short-duration load
curtailment measure is ineligible for an incentive under PON 620-01,
but the shifting of processes to off-peak is acceptable. The use of
automatic means to control the measures installed under this component
is not required, but encouraged, where practical. See Section II,
Program Requirements for a complete description of eligibility requirements
and program administration. NYSERDA's incentive will be the lesser
of 75% of Eligible Project Cost or the incentives set forth in Table
1, with the exception of Direct Load Control projects in Con-Edison
service territory, which will be funded the lesser of 100% of Eligible
Project Costs or the incentives set forth in Table 1.
Dispatchable Emergency Generator Initiatives (DEGI) result
in reduced electric system demand, at times of capacity shortfall,
by allowing owners of existing emergency/backup generators to offload
all, or a portion of their electrical needs to their own generators,
in response to an emergency communication from the New York Independent
System Operator's Emergency Demand Response Program (NYISO's EDRP)
or a Transmission Owner's load reduction program. To receive an incentive
under this program, an Eligible Contractor must show for each application:
registration or proof of participation, by each participating Facility,
in either the NYISO's EDRP or a Transmission Owner's load reduction
program; that each participating Facility is an electric distribution
customer within the Con Edison service territory; and that each participating
Facility pays the System Benefits Charge. Electricity from the emergency
generators shall not be fed into the utility system grid. Eligible
measures to enable critical dispatch of emergency generators in the
Con Edison service territory in response to an emergency communication
from NYISO's EDRP or a Transmission Owner's load reduction program
include: testing and tuning of emergency generators, rewiring circuits,
installation of transfer switchgear, environmental permitting, selective
use of catalytic reduction technologies, stack modifications, operational
improvements, incremental cost of Ultra Low-Sulfur Fuel, and implementation
of natural gas dual-fuel options. Other expenses related to implementing
measures to enable emergency/backup generators to be dispatched under
the NYISO EDRP or a Transmission Owner's load reduction program will
be considered on a case-by-case basis. The use of automatic means
to control the operation of emergency generators is not required,
but encouraged, where practical. NYSERDA seeks to minimize environmental
impacts associated with the use of emergency generators for this program.
The purchase or installation of new generation equipment is ineligible
for incentives under this program, but may be eligible under other
NYSERDA programs. Operation of existing emergency/backup generators
is limited to a response to an emergency communication from NYISO's
EDRP or a Transmission Owner's load reduction program. Contractors
must self certify that all Facilities with generators have applied
for or received all required permits necessary to operate the generators.
The DEGI component is only available to customers in the Con Edison
service territory. See Section II, Program Requirements for a complete
description of eligibility requirements and program administration.
NYSERDA's incentive will be the lesser of 100% of Eligible Project
Cost or the incentives set forth in Table 1.
Interval Meters (IM) result in electric load reductions through
the purchase and installation of Interval Meters by customers allowing
for participation in load reduction programs such as the NYISO's demand
response programs, a Transmission Owner's load reduction program or
other load management programs offered by Load Serving Entities (LSEs)
or Customer Service Providers (CSPs), including real time pricing.
Eligible Project Costs under this component are limited to individual
metering systems that are connected to the following in accordance
with NYISO EDRP regulations: 1) main electrical feeds (i.e. utility
service entrance or master meter point), 2) equipment that can reasonably
be curtailed in an emergency, or 3) emergency generator equipment.
See Section II, Program Requirements for a complete description of
eligibility requirements and program administration. NYSERDA's incentive
will be the lesser of 75% of Eligible Project Cost or the incentives
set forth in Table 1, with the exception of selected IM projects,
which will be funded the lesser of 100% of project cost or the incentives
set forth in Table 1.
Eligible Contractors are strongly encouraged to aggregate facilities
before applying for these incentives. All incentives will be paid
directly to the Contractor and are expected to be shared with the
end-use building owners or operators, either through direct payment,
through the provision of services, or through the installation of
equipment.
Eligible Contractors should also consider investigating other New
York Energy $martSM programs, including the Commercial/Industrial
Performance Program, the New Construction Program, Smart Equipment
Choices, and the Loan Program. These programs offer incentives for
the purchase and installation of energy efficient equipment. See NYSERDA's
website (www.nyserda.org) for more information on each of these programs.
B. AVAILABLE FUNDS
NYSERDA has up to $10.5 million available for measures under this
solicitation.
Incentive awards will be processed on a first-come, first-served basis
until all funds are committed, or through October 1, 2002, whichever
is earlier. Contractors awarded an incentive will be issued one or
more Purchase Orders from NYSERDA. The Applicant Checklist is located
in Appendix A, Facility Data Sheets are located in Appendices B1-B4,
sample Purchase Orders are located in Appendix C, a suggested Technical
Assessment outline is attached as Appendix D, and a Contractor Checklist
is located in Appendix E.
The program terms offered through this PON are effective as of August
2, 2001.
All Purchase Orders will expire on February 1, 2003, unless the
Contractor provides written justification acceptable to NYSERDA for
the delay in completing the Project. NYSERDA will not make payment
on an expired Purchase Order. Eligible Project Costs must be incurred
between August 2, 2001 and December 31, 2002.
C. DEFINITIONS
Applicant - Any entity submitting an application under this solicitation.
Contractor - Any Applicant that is awarded an incentive under this
solicitation.
Curtailment Service Provider (CSP) - A CSP is a load aggregator,
energy service company (ESCO), or electric utility authorized, but
not required, to provide load reductions under the New York Independent
System Operator's Emergency Demand Response Program (NYISO's EDRP),
or its Day Ahead Demand Response Program (DADRP).
Direct Load Control (DLC) - A load reduction strategy that can interrupt
consumer load or modify settings of equipment at the time of a NYISO
or TO peak demand period, through direct control at an aggregated
set of Facilities, by way of centrally dispatched communication/control.
Notwithstanding any other provisions of this solicitation, DLC Projects
are eligible for all building types.
Eligible Contractor - An Eligible Contractor must be capable of,
or must retain services capable of developing a summer peak demand
reduction Project, and implementing all necessary measures. Eligible
Contractors include individual building owners or operators, lease
holders, energy services companies, load serving entities, transmission
and/or distribution utilities, CSPs, equipment installers, engineering
firms, and energy management firms. Eligible Contractors who are not
individual building owners or operators are expected to develop their
own contractual relationship with their customers.
Eligible Project Costs - Incurred costs associated with the development
and implementation of the measures necessary to achieve the Project's
objectives, in accordance with the Purchase Order, Exhibits A and
B, and as outlined in this Program Opportunity Notice. Eligible Project
Costs do not include ongoing expenses such as subscription fees, software
licensing fees, service/maintenance fees, communications/internet
fees, etc.
Facility - The location where the work is being proposed. To be
eligible for this program, a Facility must pay into the System Benefits
Charge.
Field Verification - The final site visit, performed by the NYSERDA
Consultant, to verify that the measures identified in the Technical
Assessment have been installed, are operational, and are capable of
delivering the kW reduction as documented in the Technical Assessment.
Interval Meters - The Interval Meters component includes two distinct
elements: meters that capture energy use information more complex
than mere tracking of accumulated flow; and communication systems
that capture and communicate energy use information. Metering systems
that offer maximum functionality and options, as well as, effectively
integrating both elements, enable the customer more immediate access
to detailed consumption information. A PSC approved meter that is
capable of data logger communications or a meter that satisfies NYISO's
EDRP reporting requirements is eligible.
Load Serving Entity (LSE) - Any entity authorized or required by
law, regulatory authorization or requirement, agreement, or contractual
obligation to supply energy, capacity and/or ancillary services to
retail end users located within the New York Control Area (NYCA),
including NYISO direct customers.
NYISO - New York Independent System Operator.
NYISO's EDRP - New York Independent System Operator's Emergency Demand
Response Program.
NYISO's DRP - New York Independent System Operator's Demand Response
Programs, including the Day Ahead Demand Response Program (DADRP),
Emergency Demand Response Program (EDRP), Special Case Resources (SCR),
Unforced Capacity Program (UCAP), and virtual bidding.
NYSERDA Consultant - An engineering consultant under contract to
NYSERDA to provide technical support and field verification services
for this program.
Project - The measures to be implemented at a Facility or Facilities
by the Eligible Contractor applying for an incentive under this solicitation.
Qualifying Generators - All customer owned generators, model year
1995 or newer; or all model year 1994 and older generators that demonstrate
either by generator specific manufacturer's data or through emissions
testing, that NOx emissions do not exceed 35 pounds per megawatt-hour
(lb/MWh). Emissions testing methods for test and tune purposes should
be conducted consistent with industry established protocols (such
as the American Society for Testing and Materials [ASTM] D6522-00)
and applicable DEC regulations.
Summer Peak Demand Reduction Period - May 1 to October 31, during
the hours of 11:00 AM to 8:00 PM.
Technical Assessment (TA) - A site specific, engineering or feasibility
study describing peak load Permanent Demand Reduction Efforts, Short-Duration
Load Curtailment Measures, and/or Dispatchable Emergency Generator
Initiatives, the methodology for determining kW demand and kWh savings,
a summary of pre- and post- installation kW demand and kWh use, and
measure costs (see Appendix D).
Transmission Owner - The public utility or authority (or its designated
agent) that owns facilities used for the transmission of energy in
interstate commerce and provides transmission service under a New
York PSC approved tariff.
Ultra Low-Sulfur Fuel - Distillate fuel oil having a sulfur content
less than, or equal to, 30 parts per million by weight.
D. INCENTIVES
Except for DLC, DEGI, and selected IM projects that qualify for greater
incentives, successful Applicants will be reimbursed the lesser of
75% of the Eligible Project Costs or the incentive caps set forth
in Table 1 as long as the Facility owner or operator contributes no
less than 25% of Eligible Project Costs. For projects that NYSERDA
is reimbursing the Applicant the lesser of 75% of Eligible Project
Costs or the incentive caps set forth in Table 1, NYSERDA reserves
the right to require documentation from the Contractor to demonstrate
that the Facility owner or operator has contributed the required minimum
payment of no less than 25% of Eligible Project Costs.
For DLC, DEGI, and selected Interval Meter projects, successful
applicants will be reimbursed the lesser of 100% of the Eligible Project
Costs or the incentive caps set forth in Table 1. See Section II.
PROGRAM REQUIREMENTS, for a complete description of incentives. Photovoltaic
(PV) Projects are eligible under the Permanent Demand Reduction component
PON 620-01. The final incentive payment will be determined, per PON
620-01 and the Purchase Order (PO), including Exhibit A, based on
an approved Technical Assessment (developed by the Contractor) and
Field Verification of equipment installed and operational, as outlined
in the Technical Assessment, and appropriate Facility specific invoices.
These incentives may be modified if the approved Technical Assessment
and approved Field Verification identify changes to the estimated
kW demand reduction. Eligible Project Costs do not include ongoing
expenses such as subscription fees, software licensing fees, service/maintenance
fees, or communications or internet fees, etc. NYSERDA reserves the
right to increase program incentives in load pocket areas of the Consolidated
Edison service territory.
Contractors must install metering and provide reports to NYSERDA
consistent with Section II. PROGRAM REQUIREMENTS outlined in each
program component description. See Section V. METERING REQUIREMENTS
and Section VI. REPORTING REQUIREMENTS.
No more than 30% of the total invoice submitted for reimbursement
shall be for project development. Project development includes administrative
costs, engineering, marketing, development of the Technical Assessment,
travel expenses, or other expenses approved by NYSERDA. With respect
to the approved Purchase Order amount, no less than 70% of the total
invoice submitted for reimbursement shall be for project implementation.
Project implementation includes only direct expenses for the purchase
and installation of equipment at the Facility, such as on-site operation
and maintenance improvements, energy management system upgrades, advanced
metering, DLC technologies, or other expenses approved by NYSERDA.
Eligible Project Costs must be specifically itemized for each Facility,
including materials and equipment expenses, staff names and titles
identified, billable hourly rate, tasks performed, and hours applied
to specific tasks. Invoice items must be specifically identified as
project development expenses or project implementation expenses. Invoice
requirements apply to all invoices submitted, including Contractor
invoices and subcontractor invoices.
TABLE 1 - Incentive Caps**
| Installed, Operational and Field Verified*
by: |
PDRE
|
SDLC
|
DEGI
|
IM
|
|
Con-Edison
Service Territory
|
Non-
Con-Edison
Service Territory
|
Con-Edison
Service Territory
|
Non-
Con-Edison
Service Territory
|
Con-Edison
Service Territory only
|
Statewide
|
| 5/31/02 |
$450/kW |
$150/kW |
$180/kW |
$60/kW |
$90/kW |
$3,000/meter |
| 7/31/02 |
NA |
NA |
$160/kW |
$50/kW |
$80/kW |
$3,000/meter |
| 12/31/02 |
$400/kW |
$130/kW |
$160/kW |
$50/kW |
$80/kW |
$3,000/meter |
* NOTE: Field Verification is not required for Interval Meter (IM)-only
Projects.
** NOTE: Except for DLC, DEGI, and selected IM projects which qualify
for greater incentives, successful Applicants will be reimbursed the
lesser of 75% of the Eligible Project Costs or the incentive caps
set forth in Table 1 as long as the Facility owner or operator contributes
no less than 25% of Eligible Project Costs. For DLC Projects, DEGI,
and selected Interval Meter applications, successful applicants will
be reimbursed the lesser of 100% of the Eligible Project Costs or
the incentive caps set forth in Table 1.
E. ELIGIBILITY RESTRICTIONS
Measures previously funded under NYSERDA's Peak Load Reduction Program
(PON 577-00) during the summer of 2001 and the Cooling Re-Commissioning
Program during the summer of 2000 are ineligible for incentives under
PON 620-01. Incentives awarded under PON 620-01 cannot pay for measures
that received incentives under other NYSERDA funded programs. Single
family residences and demonstration projects designed to pilot new
unproven technologies are ineligible.
Participants that received a Purchase Order which expired under
PON 577-00 but did not implement the funded demand reduction measures
or receive funds for the demand reduction measures under other NYSERDA
programs may apply to PON 620-01. Expenses incurred in developing
and implementing measures installed prior to August 2, 2001 are ineligible
under PON 620-01.
II. PROGRAM REQUIREMENTS
A. PERMANENT DEMAND REDUCTION EFFORTS (PDRE)
1. Eligibility
The Applicant must be an Eligible Contractor. Measures implemented
under this component are expected to be in place and operational for
at least 5 years. For PDRE incentives, measures must be operational
and reduce demand at a Facility during the entire Summer Peak Demand
Reduction Period, consistent with the measures' normal operating schedules.
All Projects with 100kW or more of summer peak demand reductions
are required to permanently install and make operational Interval
Meters. Metered data must be archived for two years, and be made available
to NYSERDA upon request, in appropriate electronic format. If this
metered data is provided via web site, the data must be made available
in read only format. Contractors shall obtain written consent from
their clients to permit NYSERDA access to this data. Data shall be
available to NYSERDA for a two-year period. This data will be used
only for internal analysis, future program development purposes, and
verification of demand reductions. All data shall be protected to
the fullest extent possible through the New York State Freedom of
Information Law.
2. Incentives
Incentives may be used for expenses incurred in developing and implementing
measures, installed on or after August 2, 2001, that permanently reduce
summer peak demand. Eligible Project Costs include engineering services,
procurement and installation of capital equipment, metering equipment,
or other NYSERDA approved expenses incurred to permanently reduce
summer peak demand. Capital equipment includes equipment that reduces
electric demand, such as heating, ventilation and air-conditioning
(HVAC) equipment, lighting equipment, controls for HVAC and lighting
equipment, motors, motor drives and PV. Demand reductions resulting
from the installation of the following fossil fuel fired generators
are ineligible for funding under this solicitation: microturbines,
electric generation, and combined heat and power equipment. PDRE measures
resulting in increased Facility emissions will be considered on a
case by case basis. To be eligible for reimbursement, PDRE measures
must be activated in an automatic mode as an integrated function of
the operation of the building systems or equipment. Only capital improvements
involving short lead times or installation periods of 6 months or
less are eligible for funding under this solicitation. Applicants
with Projects that require longer lead times for design and construction
are encouraged to investigate PON 624-01 Commercial/Industrial Performance
Program or other NYSERDA-sponsored System Benefits Charge programs.
Initially, incentive amounts will be encumbered based on the Applicant's
estimate of kW summer peak demand reduction. The final incentive payment,
per the Purchase Order (PO) and Exhibit A, will be determined based
on an approved Technical Assessment (developed by the Contractor)
and Field Verification of equipment installed and operational, as
outlined in the Technical Assessment, and appropriate Facility specific
invoices. See Section V. METERING REQUIREMENTS and Section VI. REPORTING
REQUIREMENTS. Incentives for this component are:
For Projects in the Con Edison Service Territory:
a. The lesser of 75% of Eligible Project Costs or $450/kW of summer
peak demand reduction for measures installed, operational, and Field
Verified on or before May 31, 2002.
b. The lesser of 75 % of Eligible Project Costs or $400/kW of summer
peak demand reduction for measures installed, operational, and Field
Verified on or before December 31, 2002.
For Projects Outside the Con Edison Service Territory:
a. The lesser of 75 % of Eligible Project Costs or $150/kW of summer
peak demand reduction for measures installed, operational, and Field
Verified on or before May 31, 2002.
b. The lesser of 75 % of Eligible Project Costs or $130/kW of summer
peak demand reduction for measures installed, operational, and Field
Verified on or before December 31, 2002.
3. Application Process
a. The application process begins when the Applicant submits a written
application to NYSERDA (see Appendix A and Appendix B1), on behalf
of one or more Facilities. For aggregated Projects, only one Appendix
A is required, although one Appendix B1 must be completed for each
Facility. Appendix B1 must describe each Project for a particular
Facility and indicate an estimated summer peak kW demand reduction
for each Facility.
b. If the completed application meets all program criteria, NYSERDA
will encumber funds for that Project. For PDRE, the encumbered incentive
amount will be determined by multiplying the Applicant's estimated
kW summer peak demand reduction by the appropriate incentive per kW.
At the time funds are encumbered by NYSERDA, a Purchase Order will
be issued to the Contractor with a not-to-exceed cost of the incentive.
After the Purchase Order is issued, the Contractor must develop a
Technical Assessment and send it to the NYSERDA Consultant for review
of technical accuracy and recommendations concerning the proposed
kW savings. It is the Contractor's responsibility to address and resolve
all issues raised by the NYSERDA consultant regarding the technical
accuracy of the Technical Assessment. NYSERDA will notify the Contractor
on whether or not the Technical Assessment has been approved. Upon
NYSERDA approval of the Technical Assessment, the Contractor implements
the Project. See Section IV. PROJECT IMPLEMENTATION PROCESS for requirements
to receive the incentive. The final incentive payment, per the Purchase
Order and Exhibit A, will be determined based on an approved Technical
Assessment, Field Verification of equipment installed and operational
as outlined in the approved Technical Assessment, and appropriate
Facility-specific invoices. Actual reimbursement will be the lesser
of 75% of Eligible Project Costs or the incentive caps set forth in
Table 1.
B. SHORT-DURATION LOAD CURTAILMENT MEASURES (SDLC)
1. Eligibility
The Applicant must be an Eligible Contractor. To participate in this
component, Contractors must agree to have each Facility participate
in the NYISO EDRP or a Transmission Owner's load reduction program.
Contractors must show registration or proof of each Facility's participation
in the NYISO EDRP, or a Transmission Owner's load reduction program.
For SDLC, the Project must consist of measures that are capable
of curtailing electric use during the entire Summer Peak Demand Reduction
Period, but need only operate when called upon by an emergency communication
from NYISO's EDRP or a Transmission Owner's load reduction program.
The Contractor must demonstrate to NYSERDA that it and each Facility
are capable of receiving, and responding to an emergency communication
from the NYISO's EDRP, or a Transmission Owner's load reduction program.
Each NYSERDA approved SDLC Project must have the ability to curtail
electric load at least 15 times, for a total of no less than 60 hours,
over the Summer Peak Demand Reduction Period.
2. Incentives
Incentives may be used for expenses incurred in developing and implementing
measures, installed on or after August 2, 2001, that are capable of
reducing peak demand at times of capacity shortfall in response to
an emergency communication from NYISO's DRP, or a Transmission Owner's
load reduction program.
Direct Load Control (DLC) Projects are strongly encouraged to participate
under this component, but must be a participant in the NYISO's DRP
or a Transmission Owner's load reduction program.
Eligible Project Costs include engineering services, procurement
and installation of capital equipment, metering equipment, training
of Facility staff, and development of a curtailment plan. Capital
equipment includes equipment that reduces electric demand, such as
improvements to heating, ventilation and air-conditioning (HVAC) equipment,
lighting equipment, controls for HVAC and lighting equipment, motors,
and motor drives. Other related expenses to develop and implement
projects will be considered on a case-by-case basis. The expenses
for closing of a Facility, loss of revenues due to the shut down of
a Facility as a short-duration load curtailment measure, or additional
staff costs due to shifting operations to off-peak hours are ineligible
for an incentive under this program. A Facility must be capable of
responding to a curtailment call made under the NYISO's EDRP or Transmission
Owner's load reduction program. The NYSERDA funded kW demand reduction
shall not exceed that which is registered with the NYISO or a Transmission
Owner's load reduction program. Demand reductions resulting from the
installation of new microturbines, generation, or cogeneration equipment
are ineligible under this solicitation. Initially, incentive amounts
will be encumbered based on the Applicant's estimate of kW summer
peak demand reduction. The final incentive payment, per the Purchase
Order and Exhibit A, will be determined based on an approved Technical
Assessment (developed by the Contractor), Field Verification of equipment
installed and operational, as specified in the Technical Assessment,
and appropriate Facility specific invoices. Incentives will be paid
to the Contractor regardless of whether or not there is an emergency
communication from NYISO's EDRP or a Transmission Owner's load reduction
program during the Summer Peak Demand Reduction Period. See Section
V. METERING REQUIREMENTS and Section VI. REPORTING REQUIREMENTS. Incentives
for this component are:
For Projects in the Con Edison Service Territory:
a. The lesser of 75 % of Eligible Project Costs or $180/kW of summer
load curtailment for measures installed, operational, and Field Verified
on or before May 31, 2002.
b. The lesser of 75 % of Eligible Project Costs or $160/kW of summer
load curtailment for measures installed, operational, and Field Verified
on or before December 31, 2002.
c. For Direct Load Control projects, up to 100% of the Eligible Project
Costs not to exceed the terms and dates in a. and b. above.
For Projects Outside the Con Edison Service Territory:
a. The lesser of 75 % of Eligible Project Costs or $60/kW of summer
load curtailment for measures installed, operational, and Field Verified
on or before May 31, 2002.
b. The lesser of 75 % of Eligible Project Costs or $50/kW of summer
load curtailment for measures installed, operational, and Field Verified
on or before December 31, 2002.
c. For Direct Load Control projects, up to 100% of the Eligible Project
Costs not to exceed the terms and dates in a. and b. above.
3. Minimum Project Size
Total proposed demand reduction must be at least 100 kW per Eligible
Contractor application which may include an aggregated group of Facilities.
Contractors are strongly encouraged to aggregate multiple Facilities.
Direct Load Control Projects must control an aggregated set of Facilities,
by way of centrally dispatched communication/control.
4. Application Process
a. The application process begins when the Applicant submits a written
application to NYSERDA (see Appendix A and Appendix B2) on behalf
of one or more Facilities. For aggregated Projects, only one Appendix
A is required, although one Appendix B2 must be completed for each
Facility. Appendix B2 must describe each Project for a particular
Facility and indicate an estimated summer peak kW demand reduction
for each Facility.
b. If the completed application meets all program criteria, NYSERDA
will encumber funds for that Project. For SDLC, the initial encumbered
incentive amount will be determined by multiplying the Applicant's
estimate of kW summer peak demand reduction by the appropriate incentive
per kW. At the time funds are encumbered by NYSERDA, a Purchase Order
will be issued to the Contractor with a not-to-exceed cost of the
incentive. After the Purchase Order is issued, the Contractor must
develop a Technical Assessment and send it to the NYSERDA Consultant
for review of technical accuracy and recommendations concerning the
proposed kW savings. It is the Contractor's responsibility to address
and resolve all issues raised by the NYSERDA consultant regarding
the technical accuracy of the Technical Assessment. NYSERDA will notify
the Contractor whether or not the Technical Assessment has been approved.
Upon NYSERDA approval of the Technical Assessment, the Contractor
implements the Project. See Section IV. PROJECT IMPLEMENTATION PROCESS
for requirements to receive the incentive. The final incentive payment,
per the Purchase Order and Exhibit A, will be determined based on
an approved Technical Assessment, Field Verification of equipment
installed and operational as outlined in the approved Technical Assessment,
and appropriate Facility-specific invoices. Actual reimbursement will
be the lesser of 75% of Eligible Project Costs or the incentive caps
set forth in Table 1 (Direct Load Control projects, up to 100% of
the Eligible Project Costs).
c. All Projects must be registered in the NYISO EDRP or a Transmission
Owner's load reduction program. However, incentives will be paid to
the Contractor regardless of whether or not there is an emergency
communication from NYISO's EDRP or a Transmission Owner's load reduction
program during the Summer Peak Demand Reduction Period.
C. DISPATCHABLE EMERGENCY GENERATOR INITIATIVES (DEGI)
Emergency/backup generators can provide a critical cushion for system
reliability during the Summer Peak Demand Reduction Period since the
equipment is already in place and their operation can be initiated
quickly. However, emergency generator emission rates are typically
much higher than central station power plants and will likely run
during high ozone periods. NYSERDA fully intends to mitigate adverse
environmental impacts from the use of emergency generators funded
under this program. To minimize emissions impacts, NYSERDA expects
Contractors to develop and implement with the cleanest-burning emergency
generators first, leaving the dirtiest diesel-fired generators as
a last resort.
1. Eligibility
Only Projects within the Con Edison service territory are eligible
for incentives under the DEGI component.
The Applicant must be an Eligible Contractor. To participate in
this component, the Contractor and the Facility must agree to participate
in the NYISO EDRP or a Transmission Owner's load reduction program.
The purchase or installation of new generation equipment is ineligible
for incentives under this PON. However, new generation equipment may
be eligible for incentives under other SBC-funded programs. See NYSERDA's
website for further information.
For DEGI, the measures must be capable of operating during the entire
Summer Peak Demand Reduction Period, but need only operate when it
receives an emergency communication from NYISO's EDRP or a Transmission
Owner's load reduction program to do so. Contractors must demonstrate
to NYSERDA that they are capable of receiving and responding to an
emergency communication from NYISO's EDRP or a Transmission Owner's
load reduction program.
Each NYSERDA approved DEGI Project must have the ability to operate
at least 15 times, for a total of no less than 60 hours, and no more
than 200 hours, over the Summer Peak Demand Reduction Period.
2. Incentives
Incentives may be used for expenses incurred in developing and implementing
measures installed on or after August 2, 2001 and needed to prepare
emergency generators to be operated in response to an emergency communication
from NYISO's EDRP or a Transmission Owner's load reduction program.
The NYSERDA funded demand reduction shall not exceed that which is
registered with the NYISO's EDRP or a Transmission Owner's load reduction
program.
Eligible Project Costs include engineering services, procurement
and installation of metering equipment, testing and tuning of emergency
generators, improvements to reduce environmental impacts, incremental
cost of Ultra Low-Sulfur Fuel over existing permit requirements, rewiring
circuits, installation of transfer switchgear, environmental permitting,
selective use of catalytic reduction technologies, stack modifications,
operational improvements, and implementation of natural gas dual-fuel
options. Other related costs will be considered on a case-by-case
basis.
A Facility must be capable of responding to a curtailment call made
under the NYISO's EDRP or a Transmission Owner's load reduction program.
Demand reductions resulting from the installation of new microturbines,
generation, or cogeneration equipment are ineligible under this solicitation.
Initially, incentive amounts will be encumbered based on the Applicant's
estimate of kW summer peak demand reduction. The final incentive payment,
per the Purchase Order and Exhibit A, will be determined based on
an approved Technical Assessment (developed by the Contractor), Field
Verification of equipment installed and operational, as specified
in the Technical Assessment, and appropriate Facility specific invoices.
See Section IV. PROJECT IMPLEMENTATION PROCESS for requirements to
receive the incentive. Incentives will be paid to the Contractor regardless
of whether or not there is an emergency communication from NYISO's
EDRP or a Transmission Owner's load reduction program during the Summer
Peak Demand Reduction Period. See Section V. METERING REQUIREMENTS
and Section VI. REPORTING REQUIREMENTS. Incentives for this component
are:
For Projects in the Con Edison Service Territory ONLY:
a. The lesser of 100% of Eligible Project Costs or $90/kW of dispatchable
emergency generation for Qualifying Generators installed, operational,
and Field Verified on or before May 31, 2002.
b. The lesser of 100% of Eligible Project Costs or $80/kW of dispatchable
emergency generation for Qualifying Generators installed, operational,
and Field Verified on or before December 31, 2002.
Eligible Contractors may modify or tune emergency generators in
order to meet emission requirements of a Qualifying Generator. Generator
specific manufacturer's data is considered adequate documentation
for the Contractor to demonstrate that the equipment will meet the
NOx threshold requirement.
3. Required Mitigation Measures
To further mitigate environmental impacts of this program, NYSERDA
will purchase and retire NOx allowances equal to twice the total calculated
NOx emissions generated from this component. NOx emissions will be
based on the actual hours of operation of the emergency generators
and a NOx emission rate of 35 lb/MWh for all participants of this
solicitation component. The allowances will be purchased in one block
at the end of the Summer Peak Demand Reduction Period.
4. Minimum Project Size
Total proposed summer peak dispatchable emergency generation must
be at least 500 kW per Eligible Contractor application which may include
an aggregated group of Facilities. Contractors are strongly encouraged
to aggregate multiple Facilities.
5. Application Process
a. The application process begins when the Applicant submits a written
application to NYSERDA (see Appendix A and Appendix B3) on behalf
of one or more Facilities. For aggregated Projects, only one Appendix
A is required, although one Appendix B3 must be completed for each
Facility. Appendix B3, Page 2 must be completed for all emergency
generator(s) applied for at each Facility. Use additional Appendix
B3, Page 2's as necessary. Appendix B3 must describe each Project
for a particular Facility and indicate an estimated summer kW capacity
proposed for dispatch to each Facility.
b. If the completed application meets all program criteria, NYSERDA
will encumber funds for that Project. For DEGI, the initial encumbered
incentive amount will be determined by multiplying the Applicant's
estimate of kW summer peak demand reduction by the appropriate incentive
per kW. At the time funds are encumbered by NYSERDA, a Purchase Order
will be issued to the Contractor with a not-to-exceed cost of the
incentive. After the Purchase Order is issued, the Contractor must
develop a Technical Assessment and send it to the NYSERDA Consultant
for review of technical accuracy and recommendations concerning the
proposed kW savings. It is the Contractor's responsibility to address
and resolve all issues raised by the NYSERDA Consultant regarding
the technical accuracy of the Technical Assessment. NYSERDA will notify
the Contractor whether or not the Technical Assessment has been approved.
Upon NYSERDA approval of the Technical Assessment, the Contractor
implements the Project. Contractors must self certify that all Facilities
with generators have applied for or received all required permits
necessary to operate the generators. See Section IV. PROJECT IMPLEMENTATION
PROCESS for requirements to receive the incentive. The final incentive
payment, per the Purchase Order and Exhibit A, will be determined
based on an approved Technical Assessment, Field Verification of equipment
installed and operational as outlined in the approved Technical Assessment,
and appropriate Facility-specific invoices. Actual reimbursement will
be the lesser of 100% of Eligible Project Costs or the incentive caps
set forth in Table 1.
c. All Projects must be registered in the NYISO EDRP or a Transmission
Owner's load reduction program. However, incentives will be paid to
the Contractor regardless of whether or not there is an emergency
communication from NYISO's EDRP or a Transmission Owner's load reduction
program during the Summer Peak Demand Reduction Period.
D. INTERVAL METERS (IM)
1. Eligibility
NYSERDA will provide incentives for the purchase and installation
of Interval Meters, installed on or after August 2, 2001, by customers
who are capable of participating in load reduction programs such as
a NYISO DRP, a Transmission Owner's load management program, or other
load reduction programs offered by LSEs, or CSPs, including real time
pricing. Eligible Project Costs under this component are limited to
individual metering systems that are connected to the following in
accordance to NYISO EDRP regulations: 1) main electrical feeds (i.e.
utility service entrance or master meter point), 2) equipment that
can reasonably be curtailed in an emergency, or 3) emergency generator
equipment. Any Interval Meter enabling less than a 50 kW reduction
will be considered on a case-by-case basis.
2. Incentives
For Interval Meters Installed Statewide:
a. The lesser of 100 % of Eligible Project Costs or $3,000 per Interval
Meter, for meters installed and operational on or before July 31,
2002 and for which the Applicant can provide proof of participation
in one of the NYISO DRPs, or a Transmission Owner's load reduction
program, or other load reduction programs offered by LSEs, or CSPs,
including real time pricing.
b. The lesser of 75 % of Eligible Project Costs or $3,000 per Interval
Meter, for meters installed and operational on or before December
31, 2002.
3. Application Process
a. The application process begins when the Applicant submits a written
application to NYSERDA (see Appendix A and Appendix B4) on behalf
of one or more Facilities. For aggregated Projects, only one Appendix
A is required, although one Appendix B4 must be completed for each
Facility. Appendix B4 must describe each Project for a particular
Facility. The estimated demand reduction for each Facility, as a result
of the meter installation, must be provided unless the demand reductions
are already provided as part of an application for another program
component (PDRE, SDLC, or DEGI). If the completed application meets
all program criteria, NYSERDA will encumber funds for that Project.
b. At the time funds are encumbered, a Purchase Order will be issued
to the Contractor with a not-to-exceed cost of the incentive. After
the Purchase Order is issued, the Contractor must implement the Project.
See Section IV. PROJECT IMPLEMENTATION PROCESS for requirements to
receive the incentive. Actual reimbursement will be the lesser of
75% of Eligible Project Costs or the incentive caps set forth in Table
1. However, up to 100% of Eligible Project Costs will be provided
for Interval Meters installed and operational on or before July 31,
2002 and for which the Applicant provides proof of participation in
one of the NYISO DRPs, or a Transmission Owner's load management program,
or other load reduction programs offered by LSEs, or CSPs, including
real time pricing.
III. PROGRAM INCENTIVE CAPS
The total incentive per Contractor under this Program will not exceed
20% of the total funding for this solicitation (initial Contractor
cap - $3.5 million). Contractor caps may be adjusted based on program
activity and funding resources.
The total incentive per Facility for measures under this Program
will not exceed 5% of the total funding for this solicitation (initial
Facility cap - $890,000). Facility caps may be adjusted based on program
activity and funding resources.
IV. PROJECT IMPLEMENTATION PROCESS
A. Non Interval Meter Projects
Unless noted otherwise, for Permanent Demand Reduction Efforts (PDRE),
Short-Duration Load Curtailment measures (SDLC), and Dispatchable
Emergency Generator Initiatives (DEGI), each of the following steps
must be completed to receive payment. A checklist is provided in Appendix
E.
1. Eligible Contractor submits application to NYSERDA on or before
October 1, 2002.
2. Once a Purchase Order is issued, a NYSERDA Consultant will be
assigned to the Contractor's Project at no cost to the Contractor.
This Consultant is assigned to the Project to review demand reduction
measures identified and recommended in the Technical Assessment and
to complete a Field Verification. NYSERDA will send a notice to the
Contractor with the NYSERDA Consultant's contact information, as well
as notify the NYSERDA Consultant of the Contractor's contact information.
3. The Contractor must submit a completed Technical Assessment to
their assigned NYSERDA Consultant for a review of technical accuracy
within 35 business days of receipt of the Purchase Order, otherwise,
the Purchase Order may be voided. The Technical Assessment provides
appropriate technical documentation and backup data to support the
estimated kW demand reduction provided in Appendix B of the application
. See Appendix D for Suggested Technical Assessment Outlines.
4. The NYSERDA Consultant reviews the Technical Assessment for technical
accuracy and provides recommendations concerning the proposed kW savings
within seven (7) business days of the Technical Assessment receipt.
It is the Contractor's responsibility to address and resolve all issues
raised by the NYSERDA Consultant regarding the technical accuracy
of the Technical Assessment.
5. The NYSERDA Consultant provides its recommendations to NYSERDA.
NYSERDA will notify the Contractor on whether or not the Technical
Assessment is approved. If approved by NYSERDA, a notice-to-proceed
will be sent to the Contractor, stating the estimated kW demand reduction.
Any Contractor proceeding with implementation of the Project before
receiving a notice-to-proceed from NYSERDA does so at their own risk.
6. Upon receipt of the notice-to-proceed, the Contractor shall proceed
to implement measures, as specified in the approved Technical Assessment.
7. Upon Project completion, the Contractor must contact their assigned
NYSERDA Consultant to schedule the post-installation Field Verification.
Once the Contractor notifies the NYSERDA Consultant of Project completion,
the NYSERDA Consultant must, within seven (7) business days, conduct
a post-installation Field Verification visit.
8. Upon completion of the Field Verification, the NYSERDA Consultant
will provide written documentation to NYSERDA summarizing its technical
review of the Project installation and providing a recommended final
adjusted kW of summer peak demand reduction. If approved by NYSERDA,
a notice-to-invoice will be sent to the Contractor, verifying that
completed measures have been approved and stating the final adjusted
kW demand reduction based on actual operation of the equipment. If
the kW summer peak demand reduction from the Field Verification is
greater than the amount estimated in Appendix B of the application,
the Purchase Order will be amended to reflect the increased incentive,
provided sufficient funds still exist in PON 620-01.
9. Upon receipt of complete invoices and documentation, the Contractor
receives the incentive award in a one lump sum payment. Deliverables
required in order to receive the one lump sum payment are: 1) a Contractor
invoice which references the Purchase Order number , 2) copies of
Facility specific vendor invoices and documentation to verify project
development and project implementation (See SECTION I. (D) INCENTIVES
and SECTION II. (A) (2) Incentives, (B) (2) Incentives, and (C) (2)
Incentives), 3) the notice-to-proceed from NYSERDA verifying approval
of the Technical Assessment, 4) the notice-to-invoice from NYSERDA
verifying post installation/operation approval of the summer peak
demand reduction measures, and 5) for Short Duration Load Curtailment
and Dispatchable Emergency Generation Initiative Projects, consistent
with requirements of those Program components, proof of registration
in a NYISO DRP or a Transmission Owner's load reduction program. See
Exhibit A attached to the Purchase Order for a complete description
of program requirements.
For Direct Load Control and DEGI projects, the incentive shall not
exceed either 100% of Eligible Project Costs, or the incentive caps
set forth in Table 1. For all other projects, the incentive shall
not exceed either 75% of Eligible Project Costs, or the incentive
caps set forth in Table 1, as long as the Facility owner or operator
contributes no less than 25% of Eligible Project Costs. Further, no
more than 30% of the total invoice submitted for reimbursement shall
be for project development. Project development includes, administrative
costs, engineering, marketing, development of the Technical Assessment,
travel expenses, or other expenses approved by NYSERDA. No less than
70% of the total invoice submitted for reimbursement shall be for
project implementation. Project implementation includes only direct
expenses for the purchase and installation of equipment at the Facility,
such as on-site operation and maintenance improvements, energy management
system upgrades, advanced metering, DLC technologies, or other expenses
approved by NYSERDA.
10. For those Contractors registered in a NYISO DRP or participating
in a Transmission Owner's load reduction program, the NYSERDA funded
kW demand reduction shall not exceed that which is registered with
the NYISO or Transmission Owner's load reduction program. All NYSERDA
funded Short Duration Load Curtailment Projects and Dispatchable Emergency
Generation Initiative Projects must be registered in the NYISO EDRP
or be participants in a Transmission Owner's load reduction program.
B. Interval Meter Projects
Each of the following steps must be completed to receive payment.
A checklist is provided in Appendix E.
1. Eligible Contractor submits application to NYSERDA.
2. Once a Purchase Order is issued, the Contractor shall proceed
to have the Interval Meters installed and made operational.
3. The Contractor receives the incentive award in a one lump sum
payment. Deliverables required in order to receive the one lump sum
payment are: 1) a Contractor invoice which references the Purchase
Order number and describes the specific metering improvements and
their locations and installation points, 2) copies of Facility specific
vendor invoices (See SECTION II. (D) (2) Incentives), and 3) if requesting
100% of Eligible Project Costs, not to exceed $3,000 per Interval
Meter, proof of installation and program participation on or before
July 31, 2002 in a NYISO DRP, a Transmission Owner's load reduction
program, or other load reduction programs offered by LSEs, or CSPs,
including real time pricing. See Exhibit A attached to the Purchase
Order for a complete description of program requirements.
4. For those Contractors registered in a NYISO DRP or participating
in a Transmission Owner's load reduction program, the NYSERDA reported
kW demand reduction shall not exceed that which is registered with
the NYISO, a Transmission Owner's load reduction program, or other
load reduction programs offered by LSEs, or CSPs, including real time
pricing.
V. METERING REQUIREMENTS
All Projects participating in the SDLC and DEGI must have appropriate
metering technology installed. Metering equipment meeting the requirements
of NYISO's EDRP or a Transmission Owner's load reduction program will
be deemed adequate for this solicitation.
All projects with 100kW or more of summer peak demand reductions
are required to permanently install and make operational Interval
Meters. Metered data must be archived for two years, and be made available
to NYSERDA upon request, in appropriate electronic format. If this
metered data is provided via web site, the data must be made available
in read only format. Metered data must be made available to NYSERDA
for a two year period. Contractors shall obtain written consent from
their clients to permit NYSERDA access to this data. This data will
be used only for internal analysis, future program development purposes,
and verification of demand reductions. All data shall be protected
to the fullest extent possible under the New York State Freedom of
Information Law.
VI. REPORTING REQUIREMENTS
A. INTERMEDIATE REPORTS
For the SDLC, DEGI, and IM components, each time a Contractor or Facility
is required to submit a report to the NYISO or a Transmission Owner
for incentive payments as part of a load reduction or load management
program, a copy of that report shall be sent to Cathy Carlson at NYSERDA
within 30 days of the submission of the report to the NYISO or a Transmission
Owner.
B. FINAL REPORTS
By January 31, 2003, each Contractor participating in this Program
shall submit a final report to NYSERDA detailing:
1. Total kW contracted for this Program,
2. Actual system coincident peak demand reductions realized,
3. Number and duration of each of NYISO's EDRP or a Transmission Owners
load reduction program's emergency communications (for Short-Duration
Load Curtailment Measures and Dispatchable Emergency Generator Initiatives
only),
4. Number and duration of each peak demand reduction delivered in
response to each NYISO EDRP or Transmission Owners load reduction
program's emergency communication (for SDLC and IM measures only),
and
5. Number, duration and total kW dispatched through emergency generators
for each of NYISO's EDRP or a Transmission Owners load reduction program's
emergency communications (for Dispatchable Emergency Generator Initiatives
only).
Failure to provide such reports will render the Contractor ineligible
for NYSERDA's anticipated 2003 Peak Load Reduction Program.
VII. PROGRAM EVALUATION
NYSERDA may require Contractors who participate in PON 620-01 to
respond to surveys and to provide feedback through program evaluations
to assess program effectiveness.
VIII. NON-COMPLIANCE
Contractors will be deemed to be in non-compliance with this program
for any of the following: 1) Contractors fail to meet at least 80%
of demand reductions or dispatched emergency generation, as contracted
by the Purchase Order, or 2) Contractors fail to submit the final
report as required in Section VI. REPORTING REQUIREMENTS of this solicitation,
or 3) Contractors fail to submit copies of NYISO's EDRP or a Transmission
Owners load reduction program's report to NYSERDA as required in Section
VI. REPORTING REQUIREMENTS of this solicitation. Contractors deemed
to be in non-compliance will become an ineligible Contractor for NYSERDA's
anticipated 2003 Peak Load Reduction Program.
IX. LIMITATIONS
Measures for which expenses have been incurred prior to August 2,
2001 are ineligible for incentives. Measures funded under other New
York Energy $martSM programs are ineligible for incentive
under this solicitation.
Measures previously funded under NYSERDA's Peak Load Reduction Program
(PON 577-00) during the summer of 2001 and the Cooling Re-Commissioning
Program during the summer of 2000 are ineligible for incentives under
PON 620-01. Incentives awarded under PON 620-01 cannot pay for measures
that received incentives under other NYSERDA funded programs. Single
family residences and demonstration projects designed to pilot new
unproven technologies or strategies are ineligible.
NYSERDA's New York Energy $martSM Loan Program
can only be used to finance the cost of measures in excess of the
incentives paid for the same measures under the Peak-Load Reduction
Program.
The Contractor is responsible for obtaining all required local,
state, and federal permits, and is responsible for complying with
all applicable building, health, and safety codes.
All Purchase Orders will expire on February 1, 2003 unless the Contractor
provides written justification acceptable to NYSERDA for the delay
in completing the Project. NYSERDA will not make payment on an expired
Purchase Order. Eligible Project Costs must be incurred between August
2, 2001 and December 31, 2002.
X. DISCLAIMER
NYSERDA's receipt and acceptance of the Technical Assessment shall
not constitute any representation by NYSERDA as to the economic or
technical feasibility, operational capability, or reliability of the
information contained in the Technical Assessment. NYSERDA's payment
of the incentive to the Contractor shall in no way represent an endorsement
by NYSERDA of any findings or recommendations contained in such Technical
Assessment.
XI. APPLICATION REQUIREMENTS
Applicants must fill out the Applicant Checklist (Appendix A) and
the appropriate Facility Data Sheet(s) (Appendix B(s)), completely,
leaving no blank information. This information will be used to determine
the incentive award. For ease of use, the application package is also
available on NYSERDA's web site. Paper copies of application forms
and the application checklist must contain an original signature.
Applications aggregating two or more Facilities must list each Facility
separately on the application form, identifying the estimated summer
peak demand reduction expected at each Facility. A Facility with multiple
buildings may be aggregated into one Facility Data Sheet.
XII. GENERAL CONDITIONS
PROPRIETARY INFORMATION - Careful consideration should be
given before confidential information is submitted to NYSERDA as part
of your application. The Contractor should determine whether the information
is critical for evaluating an application or whether general, non-confidential
information, may be adequate for review purposes. The New York State
Freedom of Information Law, Public Officers Law, Article 6, provides
for public access to information NYSERDA possesses. Public Officers
Law, Section 87(d) (2) provides for exceptions to disclosure for records
or portions thereof that "are trade secrets or are submitted
to an agency by a commercial enterprise or derived from information
obtained from a commercial enterprise and which if disclosed would
cause substantial injury to the competitive position of the subject
enterprise." Information submitted to NYSERDA that the Contractor
wishes to have treated as proprietary, and confidential trade secret
information should be identified and labeled "Confidential"
or "Proprietary" on each page at the time of disclosure.
This information should include a written request to except it from
disclosure, including a written statement of the reasons why the information
should be excepted. See Public Officers Law, Section 89(5) and the
procedures set forth in 21NYCRR Part 501. Failure to follow proper
procedures may result in a delay reviewing the application.
MINORITY- AND WOMEN-OWNED BUSINESS POLICY - OMNIBUS PROCUREMENT
ACT OF 1992 - It is the policy of New York State to maximize opportunities
for the participation of New York State business enterprises, including
minority and women-owned business enterprises, as bidders, subcontractors
and suppliers on its procurement Agreements.
Information on the availability of New York subcontractors and suppliers
is available from:
Empire State Development
Division For Small Business
30 S. Pearl Street
Albany, NY 12245
A directory of certified minority and women-owned business enterprises
is available from:
Empire State Development
Minority and Women's Business Development Division
30 S. Pearl Street
Albany, NY 12245
INCENTIVE AWARD - NYSERDA may make an award based on an initial
application without discussion, or following limited discussion or
negotiations. NYSERDA may request additional data, or material to
support the application.
LIMITATION - This solicitation does not commit NYSERDA to
award a contract, pay any costs incurred in preparing a proposal,
or to procure or contract for services or supplies. NYSERDA reserves
the right to accept or reject any or all Applications received, to
negotiate with all qualified sources, or to cancel in part or in its
entirety the solicitation when it is in NYSERDA's best interest.
DISCLOSURE REQUIREMENT - The Applicant shall disclose any
indictment for an alleged felony, or any conviction for a felony within
the past five years, under the laws of the United States or any state
or territory of the United States, and shall describe circumstances
for each. When an Applicant is an association, partnership, corporation,
or other organization, this disclosure requirement includes the organization
and its officers, partners, and directors or members of any similarly
governing body. If an indictment or conviction should come to the
attention of NYSERDA after the award of a contract, NYSERDA may exercise
its stop-work right pending further investigation, or terminate the
agreement; the Contractor may be subject to penalties for violation
of any law which may apply in the particular circumstances.
| Attachments: |
| Appendix A - Applicant Checklist |
| Appendix B1- Permanent Demand Reduction Efforts
Facility Data Sheet |
| Appendix B2 - Short-Duration Load Curtailment Measures
Facility Data Sheet |
| Appendix B3 - Dispatchable Emergency Generator Initiatives
Facility Data Sheet |
| Appendix B4 - Interval Meters - Facility Data Sheet |
| Appendix C - Sample Purchase Orders; Exhibits B
& C |
| Appendix D - Suggested Technical Assessment Outlines |
| Appendix E - Contractor Checklist |
|